Defined cost
A cost reimbursable contract (sometimes called a cost plus contract) is one in which the contractor is reimbursed the actual costs they incur in carrying out the works, plus an additional fee.
Their actual costs are calculated based on their accounts and records, rather than a pre-determined rate or price. However, not all costs can be accurately determined on a project-specific basis, some costs have only been incurred due to the contractor’s inefficiency, and not all costs are recoverable under the contract.
Options (C, D, E and F) of the NEC (New Engineering Contract), EEC contract (Engineering and Construction Contract), describe the costs that can be recovered by the contractor as the ‘defined cost’, whereas the costs that cannot be recovered are described as the ‘disallowed cost’.
Very broadly, the defined cost includes payments due to subcontractors and the cost of components for other works (such as plant, equipment, people and so on), minus the disallowed cost.
The contract stipulates that only amounts incurred to provide the works are recoverable as cost components. If an amount can be classified as one component, such as ‘equipment’, then it cannot also fall within another, such as ‘people’.
There are seven cost component criteria:
- People: Those directly employed or paid by the contractor to carry out the works.
- Equipment: Items provided by the contractor and used to provide the works.
- Plant and materials: Items intended to be used and included in the works.
- Charges: Cancellation charges arising from a compensation event, payment to public authorities, specialist services, and so on.
- Manufacture and design: Only apply if they are outside the working areas and wholly or partly designed specifically for the works.
- Design: Costs for the works and equipment only.
- Insurance: Does not actually facilitate cost recovery for the contractor. Costs that would otherwise be recoverable that have been paid by the insurer to the contractor are set off against the recoverable cost.
[edit] Related articles on Designing Buildings Wiki:
- Articles of agreement.
- Cost reimbursable contract.
- Delay damages.
- Disallowed cost.
- Latham Report.
- NEC3.
- NEC contract change management systems.
- NEC early contractor involvement.
- Right to payment.
- Variations.
- Works information.
- Z clauses.
[edit] External references
Featured articles and news
A safe energy transition – ECA launches a new Charter
Practical policy actions to speed up low carbon adoption while maintaining installation safety and competency.
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.
A carbon case for indigenous slate
UK slate can offer clear embodied carbon advantages.
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.