Contractor's working schedule
Some construction contracts, in particular in the USA, require that the contractor produces a contractor’s working schedule. This is a critical path method (CPM) logic diagram used by the contractor, not only to plan the works, but also to record actual progress and to show how the remaining works will be completed. This is not a static schedule but is maintained by the contractor throughout the duration of the works and published periodically as a form of reporting.
In the UK, the Chartered Institute of Building’s (CIOB) Contract for Complex Projects (CPC 2013), requires that the contractor produces a working schedule, (sometimes referred to as the contractor’s working schedule) which CIOB describe as ‘a resource and cost-loaded critical path network’.
The working schedule is a digital, quality-controlled, critical path network, used to manage time, and updated with progress data such that it automatically calculates the construction end date for the works.
Cost management is carried out by reference to values attributed to the activities in the schedule, such that the schedule constantly calculates the value of work done to date and predicts the out-turn cost of the works. Payment is based upon work properly done according to the working schedule.
CIOB suggest that the working schedule is prepared at three levels of density. At low and medium density, activity durations may be estimated and linked with activity-related logic. At high density (the short-term look ahead) activity durations are calculated by reference to resources and achievable productivity and linked by resource and location-related logic.
NB In November 2015, the Complex Projects Contract was updated and renamed the Time and Cost Management Contract.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Activity schedule.
- Chartered Institute of Building.
- Construction contractor.
- Contract for Complex Projects
- Contractor’s master programme.
- Milestones.
- Noise nuisance.
- Programme.
- Schedule.
- Schedule of work.
- Scheduling construction activities.
- Time management of construction projects.
- Time and Cost Management Contract.
- What hours are construction sites allowed to operate?
- Workmanship in construction.
[edit] External references
Featured articles and news
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding.
Types of rapidly renewable content
From forestry to agricultural crops and their by-products.
Terraced houses and the public realm
The discernible difference between the public realm of detached housing and of terraced housing.
Put digitalisation and sustainability at the core of curricula
Project management educators are urged.
Looking back at the influence of climate events
From a designer and writer: 'There are limits to growth but no limits to development'.
Terms, histories, theories and practice.
Biophilic design and natural light
Letting in the light and natural elements into spaces.
APM Programme Management Conference 2024
Strategies for Success.
Residential takes the reins as contract awards even out
Contracts down, but remain above the last quarter of 2023.
Celebrating Eid and the largest mud-brick building.
Barry Kingscote claims prestigious CIOB CMYA Award.
The British Mosque: an architectural and social history
The story of some 1,500 mosques or more in Britain.
Heat pump refrigerants, efficiencies and impacts
R12 to R1270 what are the differences?
Global heat pump market in 2023
Challenging times with positive but modest outlook.
Beyond the infrastructure pipeline
Opportunities and chokepoints.