Assignment of choses in action
Choses in action are ‘…all personal rights of property which can only be claimed or enforced by action and not by taking physical possession.’ (ref Torkington v Magee). The term includes the benefits arising under a contract and, subject to certain qualifications, rights of action arising by reason of a breach of contract.
A chose in action can be a legal chose, for example an interim payment due under a building contract, or an equitable chose such as a legacy under a will or an interest in a partnership.
Choses in action can be assigned or transferred unilaterally, for example A the employer enters into a construction contract with B the contractor, requiring B to construct a building to a quality set out in the specification. A can, without the consent of, or indeed knowledge of B, transfer the benefit of that contract to a third party C. A is known as the assignor, B the debtor and C the assignee. Only the benefits of a contract can be assigned, not the burdens (see Nokes v Doncaster Amalgamated Collieries). The burden must be novated.
It is important to understand that the right to assign a chose in action is not derived from contract. It is a statutory right, alternatively a right arising from the rules of equity. Express conditions are commonly found in collateral warranties purporting to grant rights of assignment; these conditions are unnecessary and may actually have the effect of restricting the rights to assign.
[edit] Related articles on Designing Buildings
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.
Why construction can't afford to ignore the skills gap.
Building Safety Regulator, 19 August
Gill Kernick appointed Independent Chair of Residents’ Panel.
Connecting knowledge, technology and conservation
Building competence for the future of built heritage.


















Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.