CDM 2007 Health and safety file
The CDM regulations were revised in 2015 and this article is no longer current. It is provided here for historical reference only.
For information about the CDM 2015 health and safety file, see Health and safety file.
On projects that are notifiable to the HSE, (that is, the works are likely to last longer than 30 days or involve more than 500 person days of construction), the Construction (Design and Management) Regulations (CDM regulations) require that the CDM co-ordinator:
'...prepare, where none exists, and otherwise review and update a record (“the health and safety file”) containing information relating to the project which is likely to be needed during any subsequent construction work to ensure the health and safety of any person, including the information provided in pursuance of regulations 17(1), 18(2) and 22(1)(j).',
At the end of the construction phase, the CDM co-ordinator must pass the health and safety file to the client (NB where there is partial possession or sectional completion of the works, the health and safety file may be required before all the works are complete in order to inform ongoing work).
Before work starts on site the CDM co-ordinator should discuss with the client the scope, format, structure and content of the health and safety file, as well as who should provide information, and when. There may be separate files for different premises, or one overall file, and the file can be combined with the building log book, or building owner's manual. However, the health and safety information must be easy to find, if a file is created that simply contains all information about the building then genuinely important safety issues may be overlooked.
The health and safety file need only include information important to enable future construction work to be carried out safely (including cleaning, maintenance, refurbishment, alterations and eventual demolition). It should contain content that is useful and it should be in proportion to the risks involved in the project.
It does not need to include information about the construction process (which may be included in the construction phase plan), unless it may affect future works. It does not need to include contractual information, pre-construction information or information about the normal operation of the completed structure (which may be included in the building owners manual or the building log book, ref Managing health and safety in construction, Construction (Design and Management) Regulations 2007, Approved Code of Practice page 60).
The contents of the health and safety will vary depending on the nature of the works being carried out, however, it may contain:
- A description of the project.
- A description of any residual hazards that should be managed.
- The structural principles of the design.
- Identification of any hazardous materials used.
- Procedures for the removal or dismantling of installed plant and equipment.
- Information about cleaning and maintenance equipment.
- A description of significant services and their location.
- Information and as-built drawings of the structure, plant and equipment.
The health and safety file must be kept up to date, and clients must ensure that the file is available for inspection in the event future work. If work is done to premises where a health and safety file already exists, the health and safety file should be updated if necessary (and any gaps filled), even if the work is not notifiable.
The health and safety file is normally kept for the lifetime of the building, meaning that it should be passed on to the new owners if the building is sold, and the new owners should be informed of its purpose and importance.
There are no restrictions to the format that it has to be kept in, but it would be wise to ensure it is backed up.
If the premises, or part of it are leased, then the health and safety file to must be made available to the leaseholder. If there are multiple leaseholders, then those parts of the health and safety file relevant to the part of the building leased by each leaseholder must be made available to them. In multi-occupancy situations, for example where a housing association owns a block of flats, the owner should keep and maintain the file, but ensure that individual flat occupiers are supplied with health and safety information concerning their home.
[edit] Related articles on Designing Buildings Wiki
- Building log book.
- Building owner's manual.
- CDM.
- CDM co-ordinator.
- CDM planning period.
- Construction phase plan.
- Defects liability period.
- Demolition.
- Health and safety.
- Notify HSE (Form F10).
- Personal protective equipment.
- Pre-construction information.
- Principal contractor.
- Soft landings.
- Technical guide.
[edit] External references
- Full copy of the CDM regulations.
- Managing health and safety in construction, Construction (Design and Management) Regulations 2007, Approved Code of Practice. The main headings for the Health and Safety Files are included in Appendix 3.
- Regulation 10 (Pre construction information).
Featured articles and news
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.