Architect's instruction
Construction contracts generally give the contract administrator the power to issue instructions to the contractor. These instructions can be called ‘contract administrator’s instructions’ or ‘architect’s instructions’ (AI). We have used the terms ‘architect’ and ‘architect’s instruction’ below, but they could easily be replaced with ‘contract administrator’ and ‘contract administrator’s instruction’.
Broadly, Instructions may be given:
- To vary the works.
- To postpone the works.
- To remedy workmanship, goods or materials which are not in accordance with the contract.
- To sanction a variation made by the contractor.
- In relation to the expenditure of provisional sums.
- To open up work for inspection.
- To carry out tests.
- To exclude persons from the site.
The contractor must comply with the instructions within certain limitations. The contractor has the right to ‘reasonably object’ to an instruction, and instructions can only be given as empowered by the contract. On receipt of an instruction, the contractor may ask the architect to inform them which conditions empower them to make that instruction. Disagreement about the validity of an instruction may result in a dispute being deemed to have arisen, and the dispute resolution procedures of the contract will then come into force.
If an instruction requires a variation in design to be carried out by the contractor (such as on a design and build project), the instruction may be considered to alter the employer’s requirements.
If an instruction constitutes a variation, then the contractor may be required to give a variation quotation, and the works described in the instruction will not begin until the architect has confirmed their acceptance of the quotation.
If the contractor does not follow an instruction, the architect may be required to issue a 'notice to comply' to the contractor. If they still fail to comply, the architect can instruct others to carry out the work and the contractor will be liable for any additional costs incurred. It is important therefore that such costs are properly recorded, and if possible a range of quotes obtained.
Contracts can be vague about the nature of instructions, other than that they should be given in writing. They should also be dated and signed. There are various instruction pro-forma that can be purchased. It is sensible to send an instruction by recorded delivery, or to confirm its receipt in the minutes of subsequent meetings.
If an instruction is given verbally, either the architect should subsequently confirm the instruction in writing, or the contractor should confirm it in writing, and unless the architect tells the contractor that the instruction is incorrect, then the contractor’s description of the instruction will stand. See Confirmation of verbal instruction (CVI) for more information.
Where an instruction is given to open up work or to carry out tests, costs incurred will be added to the contract sum unless they were provided for in the contract bills, or if the work opened up or tested proves to be defective. If such an instruction is given because other similar work, materials or goods were defective, then no addition will be made to the contract sum as long as the instruction is reasonable.
[edit] Related articles on Designing Buildings
- Adjudication.
- Alternative dispute resolution.
- Arbitration.
- Architect.
- Confirmation of verbal instruction.
- Contract administrator.
- Contract sum.
- Compensation events.
- Defects.
- Defects liability period.
- Extension of time.
- Instruction.
- Mediation.
- Provisional sums.
- Relevant event.
- Variations.
- Work instruction.
Featured articles and news
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
70+ experts appointed to public sector fire safety framework
The Fire Safety (FS2) Framework from LHC Procurement.
Project and programme management codes of practice
CIOB publications for built environment professionals.
The ECA Industry Awards 2024 now open !
Recognising the best in the electrotechnical industry.
Sustainable development concepts decade by decade.
The regenerative structural engineer
A call for design that will repair the natural world.
Buildings that mimic the restorative aspects found in nature.
CIAT publishes Principal Designer Competency Framework
For those considering applying for registration as a PD.
BSRIA Building Reg's guidance: The second staircase
An overview focusing on aspects which most affect the building services industry.
Design codes and pattern books
Harmonious proportions and golden sections.
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding..
Comments
To join the debate click 'Add a comment' above.
Dear All I would like to know if people have strong views on how and when costs should be visible to the contractor on an AI. We are using NBS Contract Administrator which allows these costs to be hidden, or displayed.If the cost of an instruction is not known at the point of instructing, surely it would be meaningless to show an arbitrary number. As such, is it ever appropriate to display costs at the point of instruction?In my experience architectural practices deal with this in differing ways, but I suspect there is an approved way of doing it.Thanks!
The consensus of opinion appears to be that whilst the display of costs attached to an AI is optional, transparency is favourable. If you have pre-negotiated a price put it into the AI but be clear what it covers, such as overheads, prelims and profit. If not negotiated state it as a "budget cost" but also define what it covers.