Architect's instruction
Construction contracts generally give the contract administrator the power to issue instructions to the contractor. These instructions can be called ‘contract administrator’s instructions’ or ‘architect’s instructions’ (AI). We have used the terms ‘architect’ and ‘architect’s instruction’ below, but they could easily be replaced with ‘contract administrator’ and ‘contract administrator’s instruction’.
Broadly, Instructions may be given:
- To vary the works.
- To postpone the works.
- To remedy workmanship, goods or materials which are not in accordance with the contract.
- To sanction a variation made by the contractor.
- In relation to the expenditure of provisional sums.
- To open up work for inspection.
- To carry out tests.
- To exclude persons from the site.
The contractor must comply with the instructions within certain limitations. The contractor has the right to ‘reasonably object’ to an instruction, and instructions can only be given as empowered by the contract. On receipt of an instruction, the contractor may ask the architect to inform them which conditions empower them to make that instruction. Disagreement about the validity of an instruction may result in a dispute being deemed to have arisen, and the dispute resolution procedures of the contract will then come into force.
If an instruction requires a variation in design to be carried out by the contractor (such as on a design and build project), the instruction may be considered to alter the employer’s requirements.
If an instruction constitutes a variation, then the contractor may be required to give a variation quotation, and the works described in the instruction will not begin until the architect has confirmed their acceptance of the quotation.
If the contractor does not follow an instruction, the architect may be required to issue a 'notice to comply' to the contractor. If they still fail to comply, the architect can instruct others to carry out the work and the contractor will be liable for any additional costs incurred. It is important therefore that such costs are properly recorded, and if possible a range of quotes obtained.
Contracts can be vague about the nature of instructions, other than that they should be given in writing. They should also be dated and signed. There are various instruction pro-forma that can be purchased. It is sensible to send an instruction by recorded delivery, or to confirm its receipt in the minutes of subsequent meetings.
If an instruction is given verbally, either the architect should subsequently confirm the instruction in writing, or the contractor should confirm it in writing, and unless the architect tells the contractor that the instruction is incorrect, then the contractor’s description of the instruction will stand. See Confirmation of verbal instruction (CVI) for more information.
Where an instruction is given to open up work or to carry out tests, costs incurred will be added to the contract sum unless they were provided for in the contract bills, or if the work opened up or tested proves to be defective. If such an instruction is given because other similar work, materials or goods were defective, then no addition will be made to the contract sum as long as the instruction is reasonable.
[edit] Related articles on Designing Buildings
- Adjudication.
- Alternative dispute resolution.
- Arbitration.
- Architect.
- Confirmation of verbal instruction.
- Contract administrator.
- Contract sum.
- Compensation events.
- Defects.
- Defects liability period.
- Extension of time.
- Instruction.
- Mediation.
- Provisional sums.
- Relevant event.
- Variations.
- Work instruction.
Featured articles and news
This weeks guest editor, Ankita Dwivedi of Firstplanit.
Fropm practice to research and the business of materials.
Terms, histories, theories and practices.
Types of work to existing buildings - repurposing of buildings
Alteration and everything else before demolition.
2023 HSE data on workplace injuries and ill health
And CIOB's response.
Building Safety Act and Secondary Legislation
Presidential update from CIAT's Eddie Weir PCIAT.
Starting pistol Statement for an election campaign?
Rates freeze, NI cuts, full expensing; early election?
Positive pressure or positive input ventilation
Could this be a remedy for condensation, damp or mould?
Unlocking a Healthier Tomorrow
Report on Social housing retrofit in Scotland 2023
Call for ministerial group and National Retrofit Delivery Plan.
The Great Transformation 1860–1920. Book review.
2023 Autumn Statement in brief with reactions
Including the devolved governments, CIOB, ECA, APM and IHBC.
Irish Life Sciences HQ, an exemplar of adaptive reuse
AT awards small to medium size project category winner.
Formal and informal adaptive re-use or new use of buildings.
Broken Record. Emissions Gap Report 2023
Temperatures hit new highs, yet world fails to cut emissions (again).
Comments
To join the debate click 'Add a comment' above.
Dear All I would like to know if people have strong views on how and when costs should be visible to the contractor on an AI. We are using NBS Contract Administrator which allows these costs to be hidden, or displayed.If the cost of an instruction is not known at the point of instructing, surely it would be meaningless to show an arbitrary number. As such, is it ever appropriate to display costs at the point of instruction?In my experience architectural practices deal with this in differing ways, but I suspect there is an approved way of doing it.Thanks!
The consensus of opinion appears to be that whilst the display of costs attached to an AI is optional, transparency is favourable. If you have pre-negotiated a price put it into the AI but be clear what it covers, such as overheads, prelims and profit. If not negotiated state it as a "budget cost" but also define what it covers.