Approximate quantities cost plan
Cost plans are generally prepared by cost consultants (often quantity surveyors). They evolve through the life of the project, developing in detail and accuracy as more information becomes available about the nature of the design, and then actual prices are provided by contractors and suppliers.
They range from very early initial cost appraisals through to tender pricing documents and the final account:
- Initial cost appraisals (studies of options prepared during the feasibility study stage).
- Elemental cost plan (prepared during the project brief stage and developed all the way through to detailed design).
- Approximate quantities cost plan (from the end of detailed design through to tender).
- Pre-tender estimate (prepared alongside tender documentation).
- Tender pricing document (strictly speaking this is not a priced document, but is part of the tender documentation issued to the contractor for pricing).
- Contract sum (agreed with the contractor during the tender period and adjusted during the construction period).
- Contract sum analysis (a break down of the contract sum prepared by the contractor on design and build projects).
- Final account (agreed during the defects liability period).
Other than initial cost appraisals, these all relate to the construction cost of the project (rather than wider project costs that the client might incur, which could include; fees, equipment costs, furniture, the cost of moving staff, contracts outside of the main works, and so on). It is important that the client makes clear what costs should be monitored by the cost consultant and what will remain within the control of the client organisation.
The approximate quantities cost plan is a development of the elemental cost plan. Unlike the elemental cost plan in which the cost of elements is broken down from the overall construction cost, based on the experience of the cost consultant and known costs of similar completed projects, the approximate quantities cost plan is a first attempt to measure defined quantities from drawings (or to take them off from a building information model).
It presents a more accurate picture of where costs are distributed, in particular it draws to the attention of designers those elements of the design that are standard and those that are not and as a consequence may be more expensive. In effect it is a priced approximate bill of quantities.
The approximate quantities cost plan should be accompanied by a schedule of assumptions made and perhaps a cash flow projection. A pre-construction whole-life cost plan may also be prepared.
The approximate quantities cost plan should form a solid base for an effective value engineering exercise.
From the point that the approximate quantities cost plan has been approved, cost control procedures can be introduced by treating changes as if they are variations.
[edit] Related articles on Designing Buildings
- Approximate bill of quantities vs approximate quantities cost plan.
- Bills of quantities.
- Budget.
- Business plan.
- Common arrangement of work sections.
- Contract sum.
- Contract sum analysis.
- Cost consultant.
- Cost control.
- Cost of building.
- Cost plans
- Elemental cost plan
- Final account.
- Initial cost appraisal.
- New Rules of Measurement.
- Order of cost estimate.
- Pre-tender estimate.
- Provisional quantity.
- Tender cost.
- Tender pricing document
- Whole-life costs.
Featured articles and news
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.





















