Addendum
In a contract, the rights and obligations are created by the acts of agreement between the parties to the contract. English law does not require a particular form to contracts, and so the terms and ultimately the risk allocation are the choice of the parties involved.
Standard Form Contracts (SFC) aim to minimise the time and cost of creating contracts, but modifications may still be required. These provisions generally come in the form of amendments, but they can also come as an addendum. These two vehicles are similar, but they are structured differently and are used in different situations.
In its simplest form, an amendment is a change to an existing contract. In some cases, it may become necessary to amend a contract due to unforeseen circumstances. For instance, if certain clauses become obsolete or the industry changes and requires the inclusion of new terms, amendments may be required.
An addendum (or the plural, addenda) is written information that has been added to the original agreement. The information in an addendum is usually incorporated into the contract when the contract is executed.
Examples of addenda in construction contracts include:
- Acceleration agreements. It is common for acceleration agreements or costs to be treated as an addendum to the building contract. Sometimes acceleration agreements can be negotiated as an addendum to the contract in lieu of extensions of time caused by elements constituting client’s risk.
- BIM addendum. This addendum may provide for an information management structure, an information manager, a BIM execution plan and BIM protocols. There may also be a risk allocation and insurance provisions in relation to infringement of copyright and data loss.
[edit] Related articles on Designing Buildings
Featured articles and news
Tackle the decline in Welsh electrical apprenticeships
ECA calls on political parties 100 days to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.