Post tender estimate
The New Rules of Measurement (NRM) are published by the Royal Institute of Chartered Surveyors (RICS). They provide a standard set of measurement rules for estimating, cost planning, procurement and whole-life costing for construction projects.
According to NRM2: Detailed measurement for building works, a post tender estimate is:
| …a cost estimate carried out after the evaluation of tenders to corroborate the funds required by the employer to complete the building project. |
A post tender estimate should be prepared after tender evaluation and any tender negotiations or tender adjustments have been completed, but before the final decision to invest is made by the client. It includes known construction costs, design team fees, other development/project costs (where these are part of the cost plan) and residual risks.
The purpose of the post-tender estimate is to confirm the amount of funding that will be required in order to complete the project, allowing the client to satisfy themselves that sufficient funding will be available. It may also be used as the control estimate during the construction process.
NB: A pre-tender estimate (PTE) is the final estimate of the likely cost of the works described by the completed tender documents. It provides a final comparison with the budget, and along with the cash flow estimate enables the client to confirm that sufficient funds are available before committing to seeking tenders. For more information see: Pre-tender estimate.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Approximate quantities cost plan.
- Bills of quantities.
- Budget.
- Cash flow projection.
- Contract sum analysis.
- Cost consultant.
- Cost plan.
- Elemental cost plan.
- Estimate.
- Initial cost appraisals.
- Investment decision maker.
- NRM2.
- Pre-tender estimate.
- Tender evaluation.
- Tender negotiation.
- Tender pricing document.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.
Why construction can't afford to ignore the skills gap.
Building Safety Regulator, 19 August
Gill Kernick appointed Independent Chair of Residents’ Panel.
Connecting knowledge, technology and conservation
Building competence for the future of built heritage.
Building Regulations and Building Safety Act
CIOB publishes free advice for non-domestic clients.
Building Safety Newsletter from MHCLG.
An extraordinary record of steel engineering worldwide.
Households living near new pylons to save on bills.
ECA warns growth must not outpace grid capacity or skills.
The role of the client and decision making
CIOB response to built environment professions call for evidence.


















Comments