Post tender estimate
The New Rules of Measurement (NRM) are published by the Royal Institute of Chartered Surveyors (RICS). They provide a standard set of measurement rules for estimating, cost planning, procurement and whole-life costing for construction projects.
According to NRM2: Detailed measurement for building works, a post tender estimate is:
…a cost estimate carried out after the evaluation of tenders to corroborate the funds required by the employer to complete the building project. |
A post tender estimate should be prepared after tender evaluation and any tender negotiations or tender adjustments have been completed, but before the final decision to invest is made by the client. It includes known construction costs, design team fees, other development/project costs (where these are part of the cost plan) and residual risks.
The purpose of the post-tender estimate is to confirm the amount of funding that will be required in order to complete the project, allowing the client to satisfy themselves that sufficient funding will be available. It may also be used as the control estimate during the construction process.
NB: A pre-tender estimate (PTE) is the final estimate of the likely cost of the works described by the completed tender documents. It provides a final comparison with the budget, and along with the cash flow estimate enables the client to confirm that sufficient funds are available before committing to seeking tenders. For more information see: Pre-tender estimate.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Approximate quantities cost plan.
- Bills of quantities.
- Budget.
- Cash flow projection.
- Contract sum analysis.
- Cost consultant.
- Cost plan.
- Elemental cost plan.
- Estimate.
- Initial cost appraisals.
- Investment decision maker.
- NRM2.
- Pre-tender estimate.
- Tender evaluation.
- Tender negotiation.
- Tender pricing document.
Featured articles and news
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing with 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
Comments