CDM 2007 Construction phase plan
The CDM regulations were revised in 2015 and this article is no longer current. It is provided here for historical reference only.
For information about the CDM 2015 construction phase plan, see Construction phase plan.
The Construction (Design and Management) Regulations 2007 (CDM regulations), required that on all notifiable projects, a principal contractor is appointed, and that they develop a construction phase plan setting out how health and safety will be managed during the construction of the project.
Notifiable projects are those which last more that 30 days or involve more than 500 person-days of construction work.
The client must not allow work on site to proceed unless a construction phase plan (CPP) has been prepared, at least for the early stages of the works, and arrangements for the development of the rest of the plan (including the incorporation of information from sub-contractors) has been established.
The construction phase plan should be specific to the project (rather than generic), concise and easy to understand (perhaps with explanatory photographs or drawings).
It might include:
- A description of the works.
- Contact details for those involved in the project.
- Roles and responsibilities.
- A description of existing information and where it can be found.
- The health and safety standards to which the works will be carried out.
- Communication, training and monitoring arrangements.
- Pre-construction issues.
- Arrangements for managing the works, such as security, traffic management, site rules and welfare arrangements.
- Assessment of risks.
- Arrangements for managing significant risks.
- Emergency procedures.
- Information about restrictions which may affect the work (such as restrictions imposed by the client).
- Arrangements for creating the health and safety file.
- Circumstances under which risk assessments or method statements should be prepared.
- Sources of other information.
A detailed list of the possible contents of the construction phase plan was published in appendix 3 of Managing Health and Safety in Construction Construction (Design and Management) Regulations 2007 Approved Code of Practice.
The construction phase plan is different from the health and safety file which is prepared by the CDM co-ordinator and provides information allowing future work to the building to be carried out safely.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Construction Management, 8 July
NEETs crisis drives interest in trades, but apprenticeships barriers remain.
Passive fire protection webinar
MEP services penetration seals.
Where its at podcast (and video) - The role of the Architectural Technologist as an Expert Witness.
More than 200 remarkable buildings added to SAVE’s Buildings at Risk register.
Government scraps pre-application consultation for Nationally Significant Infrastructure Projects.
Historic England and infrastructure
New projects offer opportunities for the historic environment and local communities.
Construction Management, 2 July
Construction deaths halve in two years.
Green Book changes to drive investment in all parts of UK.
Minimum energy efficiency standards (MEES)
CIAT briefing on response to consultations for privately rented non-domestic properties.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.
A quick, simple, and zero-bills solution to prevent overheating.


















Comments