Time and material contract (T&M)
In the United States, a time and material contract (T&M) is a type of construction contract that commits the client to pay the contractor based upon the time spent on the works, the materials used, as well as a mark-up for profit. In the UK, this type of contract is known as a cost reimbursable contract or cost plus.
This differs from a fixed price contract which commits the client to pay the contractor a lump sum fee for fulfilling the contract regardless of the amount on labour, materials, and so on used. A T&M contract is typically used on projects where it is difficult to describe the extent of the works required accurately, or where specifications and requirements are likely to change as the project progresses.
The main items that can be included in a T&M contract are:
- Labour rates: The amount that will be charged for the workforce, which may also include insurance, taxes, and so on.
- Material mark-up: It is usual for the client to be charged the retail price for materials and for a mark-up to be added by the contractor if they have a pre-agreed wholesale price with the supplier.
- Not-to-exceed: A guaranteed maximum price which places an upper limit on what the client can be charged by the contractor.
The advantages of using a T&M contract include:
- It provides the client with cost transparency and allows them to verify invoices and timesheets to ensure the costs are correct.
- It allows for greater flexibility in the extent of the works required.
- It allows works to progress even when there is no definitive plan for how it will be completed.
- It saves time in the initial estimating process which otherwise has to be done to a much higher level of detail and accuracy.
- Although there is generally a limit on their profit, the contractor can proceed knowing they are going to recover expenses with some profit, and so they can avoiding cost-cutting.
The disadvantages of using a T&M contract include:
- It can prove more risky for the client to proceed without a clear understanding of the final cost.
- It can increase the likelihood of disputes arising.
- Errors or inaccurate estimates can leave them with a low profit that may not be deemed worthwhile.
- It can necessitate more involvement from the client to ensure the contractor is motivated to progressing the works on time and within budget.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.