Time and material contract (T&M)
In the United States, a time and material contract (T&M) is a type of construction contract that commits the client to pay the contractor based upon the time spent on the works, the materials used, as well as a mark-up for profit. In the UK, this type of contract is known as a cost reimbursable contract or cost plus.
This differs from a fixed price contract which commits the client to pay the contractor a lump sum fee for fulfilling the contract regardless of the amount on labour, materials, and so on used. A T&M contract is typically used on projects where it is difficult to describe the extent of the works required accurately, or where specifications and requirements are likely to change as the project progresses.
The main items that can be included in a T&M contract are:
- Labour rates: The amount that will be charged for the workforce, which may also include insurance, taxes, and so on.
- Material mark-up: It is usual for the client to be charged the retail price for materials and for a mark-up to be added by the contractor if they have a pre-agreed wholesale price with the supplier.
- Not-to-exceed: A guaranteed maximum price which places an upper limit on what the client can be charged by the contractor.
The advantages of using a T&M contract include:
- It provides the client with cost transparency and allows them to verify invoices and timesheets to ensure the costs are correct.
- It allows for greater flexibility in the extent of the works required.
- It allows works to progress even when there is no definitive plan for how it will be completed.
- It saves time in the initial estimating process which otherwise has to be done to a much higher level of detail and accuracy.
- Although there is generally a limit on their profit, the contractor can proceed knowing they are going to recover expenses with some profit, and so they can avoiding cost-cutting.
The disadvantages of using a T&M contract include:
- It can prove more risky for the client to proceed without a clear understanding of the final cost.
- It can increase the likelihood of disputes arising.
- Errors or inaccurate estimates can leave them with a low profit that may not be deemed worthwhile.
- It can necessitate more involvement from the client to ensure the contractor is motivated to progressing the works on time and within budget.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.