Period for reply
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the contractor and client. The third edition, NEC3 was published in 2005.
Many clauses within the NEC suite of contracts establish a period within which a task must be completed by referring to defined dates such as the ‘completion date’, the ‘defects date’, and so on. Some clauses establish a period within which one of the parties must respond to a communication from the other, such as the period for the submission of quotations for compensation events, acceptance of the programme and so on. However, where no such period has been prescribed, then the ‘period for reply’ applies.
The Engineering Construction Contract (ECC) states that:
‘If this contract requires the project manager, the supervisor, or the contractor to reply to a communication, unless otherwise stated in this contract, he or she replies within the period for reply.’
The period for reply is set out in the contract data part one, completed by the employer, and replies to communications must be made within that period, unless another period is stated in the contract. Where a specific time limit is defined within the contract for a particular reply then this will take precedence over the period for reply.
If the project manager fails to reply to a communication within the period for reply, this may constitute a compensation event. If the contractor fails to reply to a communication, then an adjustment may be made to the next payment reflecting the cost to the employer.
An exception to this is where the project manager and contractor agree to an extension before the reply is due.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Articles of agreement.
- Compensation event.
- Contract conditions.
- Defects.
- Delay damages.
- Disallowed cost.
- Extension of time.
- Key dates.
- NEC3.
- NEC contract change management systems.
- NEC early contractor involvement.
- Procurement route.
- Time Risk Allowance TRA.
- Variations.
- Z clauses.
[edit] External references
- ‘The New Engineering Contract: A Legal Commentary’, McINNIS, A., Thomas Telford (2001)
Featured articles and news
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.
Comments