NEC Contract data
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration. The third edition, NEC3 was published in 2005. The fourth, and currently latest edition NEC4, was published in 2018.
The contract documents under the NEC Engineering and Construction Contract (ECC) are:
- The form of agreement.
- Conditions of contract.
- Contract data.
- Prices, activities schedules and bill of quantities.
- Works information (describing what is to be done on the site).
- Site information (describing the condition of the site before the work starts).
NEC define the contract data as information that ‘…needs to be completed as part of the necessary contract documents; in the ECC this contains details such as starting date/Completion Date/employer details/defects date and the like. It is in two parts; part one (provided by the employer) and part two (provided by the contractor).’
Part one, data provided by the employer, is completed by the employer and might include data relating to:
- Details of the employer and key personnel.
- The location of the works information and site information.
- The language and law to be adopted.
- The period for reply.
- Options for adjudication / arbitration.
- Starting date / defects date / defects correction period.
- Payment details.
- Options for compensation events.
- Risk and insurance.
- Confidentiality.
- Construction operations.
- Employees.
- Intellectual property.
- Novation.
- Termination.
- Data protection.
- Force majeure.
- Early warning / compensation events.
- Disallowable expenses.
Part two, data provided by the contractor, is completed by the contractor and might include data relating to:
- Details of the contractor and key personnel.
- The location of the programme.
- The location of works information for contractor’s design.
- The location of the activity schedule.
- Direct fee percentage.
- Subcontractor fee percentage.
- Working areas (including offices).
- Details to be included in the risk register.
- The tendered price.
- Cost components.
It is very important that the contract data is completed carefully as it is this information that structures the way the contract is administered.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing with 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.