Measurement contract
Measurement contracts (sometimes called ‘re-measurement’ or ‘measure and value’ contracts) can be used in situations where the design (or type of works) can be described in reasonable detail, but the amount cannot.
For example, excavation works where the quantity of excavation required is difficult to assess until after the works have begun, or refurbishment projects where there are some uncertainties about the works that will be required. A measurement contract might also be appropriate on projects where the design has not been completed in sufficient detail for bills of quantities to be produced.
It should be possible to describe the works in sufficient detail to determine a programme and to obtain rates from tenderers. Generally, tenderers rates will be based on drawings and approximate quantities.
The actual contract sum (sometimes called the 'ascertained final sum') cannot be determined when the contract is entered into, but is calculated on completion, based on ‘re-measurement’ of the actual work carried out and the rates tendered.
Measurement contracts can allow an early start on site, before design is complete, and they can allow changes to be made to the works relatively easily. However, there is inevitably some risk for the client as the cost of the works is not known. In effect, the client is taking the risk for any ‘unknowns’, and whilst this can result in competitive prices from contractors, the level of uncertainty for the client means that measurement contracts are rare other than on civil engineering projects.
See also: Measured term contract.
[edit] Related articles on Designing Buildings
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.
Why construction can't afford to ignore the skills gap.
Building Safety Regulator, 19 August
Gill Kernick appointed Independent Chair of Residents’ Panel.
Connecting knowledge, technology and conservation
Building competence for the future of built heritage.
Building Regulations and Building Safety Act
CIOB publishes free advice for non-domestic clients.


















Comments