Advance payment bond for construction contracts
If the client agrees to make an advance payment (sometimes referred to as a down payment) to a supplier, a bond may be required to secure the payment against default by the contractor. This is referred to as an advance payment bond (APB), advance payment guarantee or advance stage payment.
For more information, see Advance payment.
Typically on a construction project an advanced payment bond will be required by the client if the contractor requests advance payment to help them meet significant start up or procurement costs that may have to be incurred before construction begins.
For example, where the contractor has had to purchase high-value plant, equipment or materials specifically for the project. The bond will protect the client in the event that the contractor fails to fulfil its contractual obligations, for example if the contractor becomes insolvent.
An advance payment bond will normally be an on-demand bond, meaning that the bondsman pays the amount of money set out in the bond immediately on demand, without any preconditions having to be met. This is as opposed to a a conditional bond (or default bond) where the bondsman is only liable if it has been established that there has been a breach of contract.
Advance payment bonds must be very carefully drafted to set out the circumstances for payment and to make clear that they are on-demand bonds.
A ‘vesting certificate’ or ‘certificate of vesting’ may be required from the contractor (or sub-contractors or suppliers), certifying that ownership of goods, plant or materials listed in a schedule will transfer from one party to the other upon payment and confirming that they will be properly identified, separately stored, insured and are free from encumbrances (such as retention of title).
For more information see: Vesting certificate.
[edit] Related articles on Designing Buildings
- Advance payment.
- Bid bond.
- Bonds in construction contracts
- Bonds and guarantees.
- Escrow.
- Materials on site.
- Off-site goods and materials.
- Off-site goods and materials - legal issues.
- On-demand bond.
- Parent company guarantee.
- Performance bond.
- Retention.
- Retention bond.
- Vesting certificate.
- Wuhan Guoyu Logistics Group Co Ltd & Anr v Emporiki Bank of Greece SA.
- Zero-coupon bond.
[edit] External references
- Rainy Sky S.A. v Kookmin Bank.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Government approach could undermine delivery and regeneration.
World's first mass timber data centre.
The overlooked environmental aspect of data centre development.
Introduction to radon awareness
New technical information sheet published by CIOB.
Updated supplier guide can help electrical contractors engage with NHP.
CIAT confirm the winners of the 2026 architectural technology awards.
Government launches a one stop shop for flood preparedness.
Sir Edwin Lutyens: Britain's greatest architect? Book review.
CIOB publishes free template to help assess and manage risks.
ECA's reflections on Party Conference season
Burnham wants to be confident of winning before asking for a fresh mandate.
New Chief Construction and Scientific Adviser
Sergio Cavalaro, Professor of Infrastructure Systems at Loughborough University.
Building safety levy for England
CIAT publish estimator tool for members.
Water sector faces a growing crisis that could slow the delivery of vital infrastructure.

















Comments