Section 38 agreement - adoption of highways
Section 38 of the Highways Act 1980 provides that when planning consent has been granted for a new development, developers may ask the highway authority to ‘adopt’ new roads that have been constructed as part of the development, along with associated infrastructure such as drains, lighting and supporting structures.
Adoption means the highway authority agrees to undertake maintenance of the road from an agreed date at the public expense. The agreement between the highway authority and the developer is called a Section 38 Agreement.
The highway authority will be either the Secretary of State for Transport or the local highway authority.
Before entering into an agreement, the developer must have obtained planning permission, including approval of any reserved matters. The planning permission will generally include an indicative layout of the roads to be adopted.
The Section 38 Agreement may contain:
- Details of the relevant planning permission.
- Drawings indicating the extent of the area to be adopted.
- Provision for land dedication.
- Technical drawings of the works.
- A programme for the works and for the adoption.
- Provision for inspection and certification of the works.
- Agreement regarding the adoption, or not, of supporting structures.
There will be a fee associated with the agreement, covering the cost of; checking designs, preparing the agreement, inspecting the works, and ongoing maintenance of items not essential for highway purposes (commuted sums). There may also be a requirement for a bond from the developer to cover the highway authority against the possibility that the developer fails to properly complete the works, for example if they become insolvent.
The works must be constructed to a design and standard agreed by the highway authority. The developer will be responsible for carrying out the works at their own expense, and for maintenance costs until adoption.
There will generally be a 12 month maintenance period between the completion of the works and the adoption of the roads. If the development is phased, then adoption will generally take place after the final phase is completed. This is because the roads may continue to be used as a means of access by construction traffic.
The procedure necessary to reach agreement can be time consuming and protracted, and so it is desirable to enter into discussion with the highway authority as early in the project as possible.
Section 38 Agreements are often entered into alongside Section 278 Agreements, which allow developers to carry out works to a public highway. This may be necessary, for example, to provide access to a new site or to improve access to an existing site. See Section 278 Agreement for more information.
NB: Section 37 of the Highways Act 1980 enables developers to offer completed roads to the highway authority for adoption. This is generally considered a less desirable route than a Section 38 Agreement.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Adopted highway.
- Community Infrastructure Levy.
- Highways.
- Highway infrastructure and local authorities.
- Manual of Contract Documents for Highway Works.
- Planning condition.
- Planning obligation (Section 106 Agreement).
- Planning permission.
- Reserved matters.
- Section 50 agreement.
- Section 184 agreement.
- Section 215.
- Section 278 Agreement.
[edit] External references.
Featured articles and news
Landownership in England in 1909
A national valuation to fund old-age pensions.
The world’s largest Commonwealth memorial to the missing.
Long after the end of the defects liability period.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing in buildings.
Geometric form and buildings in brief
From the simple to the complex.
Understanding the changing nature of insulation
And the UK Government guidelines.
Three year action plan to improve equity, diversity and inclusion
Commitment agreed to by major built environment bodies.
The Construction Route – what needs to change?
Electrical skills, low carbon, high-tech and the building services revolution.
Deep geothermal power possibilities
Ultra-deep drilling with millimeter-wave beam technology.
BSRIA Briefing 2022- From the outside looking in
Looking at the built environment from space.
Competence requirements for principal contractors and designers
BSI standards 8671, 8672 and 8673.
Bringing life to burial grounds.
From failed modernism to twenty-minute neighbourhoods.
Design chill and design freeze
The gates process and change control.
Neuroscience for project success
Why people behave as they do. APM book.