Section 278 agreement - works to existing highways
Section 278 of the Highways Act 1980 allows a developer to carry out works to the public highway. This is generally necessary where planning permission has been granted for a development that requires improvements to, or changes to, public highways.
The agreement between the highway authority and the developer is called a Section 278 Agreement, and it may allow for items such as:
- Roundabouts.
- Priority junctions.
- Junctions with traffic lights.
- Right turn lanes.
- Improved facilities for pedestrians and cyclists.
- Improvements to existing junctions.
- Traffic calming measures.
The highway authority will be either Highways England for the strategic road network in England, or the local highway authority.
The agreement may include:
- Details of the relevant planning permission.
- The agreed design.
- Details of any bond required.
- Details of who will design and manage the works.
- The programme for the works.
- Provision for inspection and certification of the works.
- Costs.
The developer may be responsible for designing, carrying out and paying for the works to the satisfaction of the local highway authority, or the highway authority may carry out the works. The developer may also pay for all or part of works carried out by the highway authority if they are carried out in a way, at a time, or are modified to suit the developer.
In addition to the works themselves, the developer may be required to pay costs associated with:
- Making the agreement.
- Agreeing the scheme for the works.
- Permissions associated with the works.
- Land acquisition associated with the works.
- Administrative expenses incurred by the highway authority.
- Maintenance of the works (commuted sums).
If the developer is carrying out the works, there may be a requirement for a bond to cover the highway authority against the possibility that the developer fails to properly complete the works, for example if they become insolvent. The bond will be released incrementally until a twelve month maintenance period has elapsed after the works are complete.
The planning application associated with the development will generally establish the principles of the works required. The highway authority cannot then refuse to enter into an agreement for the developer to undertake the approved works as long as the works meet the appropriate standards.
If the developer fails to make agreed payments, or if the works are not carried out in accordance with the agreement, the highway authority is empowered to close the access to the site.
The procedure necessary to reach agreement can be time consuming and protracted, and so it is desirable to enter into discussion with the highway authority as early in the project as possible.
Section 278 Agreements are often entered into alongside Section 38 Agreements, which enable developers to ask the highway authority to ‘adopt’ new roads along with associated infrastructure such as drains, lighting and supporting structures. See Section 38 Agreement for more information.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Highways.
- Manual of Contract Documents for Highway Works.
- Planning condition.
- Planning obligation (Section 106 Agreement).
- Planning permission.
- Reserved matters.
- Section 38 Agreement.
- Section 50 agreement.
- Section 184 agreement.
- Section 215.
[edit] External references.
Featured articles and news
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”























Comments