Relevant matters in construction contracts
Relevant matters are referred to in some construction contracts, such as JCT contracts. A relevant matter is a matter for which the client is responsible that materially affects the progress of the works. This may enable the contractor to claim direct loss and / or expense that has been incurred. Relevant matters might include:
- Failure to give the contractor possession of the site.
- Failure to give the contractor access to and from the site.
- Delays in receiving instructions.
- Opening up works or testing works that then prove to have been carried out in accordance with the contract.
- Discrepancies in the contract documents.
- Disruption caused by works being carried out by the client.
- Failure by the client to supply goods or materials.
- Instructions relating to variations and expenditure of provisional sums.
- Inaccurate forecasting of works described by approximate quantities.
- Issues relating to CDM.
Relevant matters should not be confused with relevant events. A relevant event is an event that causes a delay to the completion date, which is caused by the client, or is a neutral event not caused by either party. Relevant events entitle the contractor to claim an extension of time; that is for the completion date to be moved. A relevant event does not necessarily entitle the contractor to claim loss and expense. Similarly, a relevant matter need not necessarily result in a delay to the completion date, and so may not always entitle the contractor to an extension of time.
NEC contracts deal with these issues under the single heading ‘compensation events’. They do not treat compensation events as an allocation of blame, but rather an allocation of risk. Any risk that is not specifically identified as being attributed to the client is borne by the contractor.
The Society of Construction Law Delay and Disruption Protocol, 2nd edition, refers to an event or cause of delay or disruption which under the contract is at the risk and responsibility of the employer, as an 'employer risk event'.
[edit] Related articles on Designing Buildings Wiki
- Compensation event.
- Consideration.
- Delays on construction projects.
- Extension of time.
- Liquidated damages.
- Loss and expense.
- Provisional sum.
- Relevant event.
- Relevant event v relevant matter.
[edit] External References
Featured articles and news
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Digital technology, transformation and cybersecurity
Supporting SMEs through Digitalisation in Construction.
Villa Wolf in Gubin, history and reconstruction. Book review.
Construction contract awards down one billion pounds
Decline over the past two months compared to the same period last year, follows the positive start to the year.
Editor's broadbrush view on forms of electrical heating in context.
The pace of heating change; BSRIA market intelligence
Electric Dreams, Boiler Realities.
New President of ECA announced
Ruth Devine MBE becomes the 112th President of the Electrical Contractors Association.