Prime cost contract
Prime cost contracts (such as JCT PPC 11) are sometimes called cost plus contracts or cost reimbursement contracts.
Prime cost contracts are used where an early or immediate start on site is required even though design information is not complete.
This method of procurement is not generally recommended, but it can be useful under particular circumstances where an immediate start on site is necessary (for example for urgent alteration or repair work, or if there has been a building failure or a fire, requiring immediate reconstruction or replacement of a building so that the client can continue to operate their business).
Tendering proceeds based on an outline specification, any drawings and an estimate of costs. The contractor is paid the prime cost (the actual cost of labour, plant and materials) and a fee for overheads and profit. The fee can be agreed by negotiation or by competition, and may be a lump sum (which it may be possible to adjust if the actual cost is different from the estimate), or a percentage of the prime cost (which it may be possible to revise if the client changes the nature of the works).
Other basis for payment are possible, including combinations of lump sum and percentage fees. For example, it might be possible to fix some elements of overheads whilst applying a percentage to other elements and to profit.
This is a high risk form of procurement for the client as they are reliant on the contractor working efficiently and procuring sub-contracts economically. Sub contracts may be procured competitively, but there may be little incentive for the contractor to secure or select economic bids. Some of these difficulties can be mitigated if a partnering relationship has been established between the client and the contractor.
NB: Some people consider that a cost reimbursable contract or cost plus contract is one in which the client takes all the risk, whereas a prime cost contract is one in which the cost of the works packages (the prime cost) are reimbursed but the main contractor takes a risk on staffing, overhead costs and profit which might be tendered on a fixed price.
[edit] Related articles
Featured articles and news
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.






















Comments
For small alternation project of 8 storey building, what is the advantage of using prime cost contract?
Unless an immediate start is needed - for example if there is some danger or urgency, it is difficult to see what the advantage would be over a traditional contract.