Prime cost contract
Prime cost contracts (such as JCT PPC 11) are sometimes called cost plus contracts or cost reimbursement contracts.
Prime cost contracts are used where an early or immediate start on site is required even though design information is not complete.
This method of procurement is not generally recommended, but it can be useful under particular circumstances where an immediate start on site is necessary (for example for urgent alteration or repair work, or if there has been a building failure or a fire, requiring immediate reconstruction or replacement of a building so that the client can continue to operate their business).
Tendering proceeds based on an outline specification, any drawings and an estimate of costs. The contractor is paid the prime cost (the actual cost of labour, plant and materials) and a fee for overheads and profit. The fee can be agreed by negotiation or by competition, and may be a lump sum (which it may be possible to adjust if the actual cost is different from the estimate), or a percentage of the prime cost (which it may be possible to revise if the client changes the nature of the works).
Other basis for payment are possible, including combinations of lump sum and percentage fees. For example, it might be possible to fix some elements of overheads whilst applying a percentage to other elements and to profit.
This is a high risk form of procurement for the client as they are reliant on the contractor working efficiently and procuring sub-contracts economically. Sub contracts may be procured competitively, but there may be little incentive for the contractor to secure or select economic bids. Some of these difficulties can be mitigated if a partnering relationship has been established between the client and the contractor.
NB: Some people consider that a cost reimbursable contract or cost plus contract is one in which the client takes all the risk, whereas a prime cost contract is one in which the cost of the works packages (the prime cost) are reimbursed but the main contractor takes a risk on staffing, overhead costs and profit which might be tendered on a fixed price.
[edit] Related articles
Featured articles and news
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”





















Comments
For small alternation project of 8 storey building, what is the advantage of using prime cost contract?
Unless an immediate start is needed - for example if there is some danger or urgency, it is difficult to see what the advantage would be over a traditional contract.