Planning constraints
Planning constraints are generally known and published planning policies that might clearly dictate if certain types of developments are acceptable or not in certain areas, such as listed buildings, conservation areas, national parks, areas of outstanding natural beauty (AONBs), greenfield sites, green belt sites and so on.
Known planning constraints are likely to lead simply to a rejection for planning or to certain planning conditions of any future planning application. Whilst planning constraints usually refers to restrictions that are known and published for a certain area, planning conditions rmost likely efers to a specific planning application.
Rather than refusing a planning application, a local authority might grant permission but with certain conditions. These conditions might require additional approvals for specific aspects of a development (such as the colour of materials) or might restrict the use of the site (for example, limiting operating hours).
A planning condition is defined in the National Planning Policy Framework (NPPF) as 'a condition imposed on a grant of planning permission (in accordance with the Town and Country Planning Act 1990) or a condition included in a Local Development Order or Neighbourhood Development Order.'
Planning constraints may impact if a development is likely to be permitted, the types, uses, shape and massing or indeed the types of materials that may be used in a development. Planning constraints may also be associated with known planning policies that are restricted under certain conditions, for example, permitted developments.
Permitted development classes may have planning constraints or restrictions placed on them, particularly in certain areas or building types such as listed buildings, conservation areas, national parks, areas of outstanding natural beauty (AONBs), greenfield sites, and green belt sites. In addition, local authorities are able to remove permitted development rights (PDRs) that are of particular significance given the character of an area by issuing an Article 4 Direction.
There may also be conditions on existing permissions preventing certain types of development. In certain cases, even though a development is permitted, prior approval of some issues might be required from the local authority. Such as specific issues relating to agricultural land, such as the purpose, siting and design of agricultural buildings as well as the construction of a private way, the siting of excavation or deposit or the siting and appearance of tanks. Similar issues arise for land used for the purposes of forestry; the erection of plants, machinery, buildings, or structures on land used as a mine; and the demolition of buildings and siting and appearance of telecommunications masts.
[edit] Related articles on Designing Buildings
- Brownfield Passport.
- Concept design report.
- Construction management: feasibility studies.
- Constrained site.
- Constraints on construction projects.
- Construction site.
- Consultation on proposed reforms to NPPF and other changes to the planning system.
- Deemed discharge of planning conditions.
- Design and access statement.
- Development appraisal.
- Discharge of planning conditions.
- Feasibility studies for construction projects.
- Golden rules for the release of land.
- Grey belt.
- Main statutory considerations and constraints.
- National Planning Policy Framework.
- Planning appeal.
- Planning condition.
- Permitted development.
- Planning enforcement.
- Planning fees.
- Planning objection.
- Planning obligation.
- Planning permission.
- RIBA Plan of Work.
- Site information for design and construction.
- The grey, the brown and the golden rules of housing.
- Traditional contract: feasibility studies.
Featured articles and news
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.
The Remarkable Pinwill Sisters: from ‘lady woodcarvers’ to professionals. Book review.
Skills gap and investment returns on apprenticeships
ECA welcomes new reports from JTL Training and The Electrotechnical Skills Partnership.
Committee report criticises UK retrofit schemes
CIOB responds to UK’s Energy Security and Net Zero Committee report.
Design and construction industry podcasts
Professional development, practice, the pandemic, platforms and podcasts. Have we missed anything?
C20 Society; Buildings at Risk List 2025
10 more buildings published with updates on the past decade of buildings featured.
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation, closing 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.