Notifiable project F10 form
The Construction (Design and Management) Regulations 2015 (CDM regulations) require that the Health and Safety Executive (HSE) must be notified of any project defined as construction under the regulations where the construction work is likely to last longer than 30 working days and have more than 20 workers working simultaneously at any point in the project, or exceed 500 person days. This can be done using an F10 form.
Regulation 6 of the CDM regulations requires that the client must give notice in writing to the HSE as soon as is practicable before the construction phase begins, or arrange for someone else to do this on their behalf.
The notice must include the details included in schedule 1 of the regulations:
- The date of forwarding the notice.
- The address of the construction site or precise description of its location.
- The name of the local authority where the construction site is located.
- A brief description of the project and the construction work that it entails.
- The following contact details of the client: name, address, telephone number and (if available) an email address.
- The following contact details of the principal designer: name, address, telephone number and (if available) an email address.
- The following contact details of the principal contractor: name, address, telephone number and (if available) an email address.
- The date planned for the start of the construction phase.
- The time allocated by the client under regulation 4(1) for the construction work.
- The planned duration of the construction phase.
- The estimated maximum number of people at work on the construction site.
- The planned number of contractors on the construction site.
- The name and address of any contractor already appointed.
- The name and address of any designer already appointed.
- A declaration signed by or on behalf of the client that the client is aware of the client duties under these Regulations.
Where details are not available (such as the details of the principal contractor) they must be provided when they are available, and in any event, before construction works begin.
The notice must also be clearly displayed in the construction site office in a comprehensible form where it can be read by any worker engaged in the construction work; and if necessary, be periodically updated.
HSE will take 10 days to process notifications by manual form. (Ref. HSE, F10 Manual input form frequently asked questions.) However, notification can now be carried out online by filling out an e-form and manual notification forms will cease to be available after 31 March 2015. Confirmation of receipt of an e-F10 form should be received shortly after submission.
[edit] Related articles on Designing Buildings
- Accident book.
- Accident report.
- CDM.
- CDM for self-builders and domestic clients.
- Competent person.
- Fee for intervention.
- First aider.
- Health and safety.
- Health and Safety Executive.
- Health and safety inspector.
- Incident reporting system.
- Inspections focus on occupational lung disease.
- Licence for Alterations for Apartment.
- Principal contractor.
- Reporting accidents and injuries on construction sites.
- Site records and registers.
- What approvals are needed before construction begins.
[edit] External references.
- HSE How to notify a project.
- Schedule 1 of the CDM regulations.
Featured articles and news
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
Welsh Recharging Electrical Skills Charter progresses
ECA progressing on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Comments