Notice of commissioning
Paragraph L1(b)(iii) of Schedule 1 to the building regulations requires that fixed building services are commissioned by testing and adjusting them as necessary to ensure that they use no more fuel and power than is reasonable in the circumstances.
Approved document L of the building regulations ‘Conservation of fuel and power’, defines ‘commissioning’ as:
‘...the advancement of a fixed building service following installation, replacement or alteration of the whole or part of the system, from the state of static completion to working order by testing and adjusting as necessary to ensure that the system as a whole uses no more fuel and power than is reasonable in the circumstances, without prejudice to the need to comply with health and safety requirements.
For each system commissioning includes setting-to-work, regulation (that is testing and adjusting repetitively) to achieve the specified performance, the calibration, setting up and testing of the associated automatic control systems, and recording of the system settings and the performance test results that have been accepted as satisfactory.’
Fixed building services means ‘…any part of, or any controls associated with—
(a) fixed internal or external lighting systems (but not including emergency escape lighting or specialist process lighting);
(b) fixed systems for heating, hot water, air conditioning or mechanical ventilation; or
(c) any combination of systems of the kinds referred to in paragraph (a) or (b).’
The building regulations require that a notice is given to the relevant building control body (BCB) that commissioning has been carried out according to a procedure approved by the Secretary of State.
The notice should include a declaration confirming that:
- A commissioning plan has been followed so that every system has been inspected and commissioned in an appropriate sequence and to a reasonable standard.
- The results of tests confirm that the performance is reasonably in accordance with the actual building design, including written commentaries where excursions are proposed to be accepted.
The use of the templates in BSRIA’s Model Commissioning Plan is a way of documenting the process in an appropriate way.
According to Approved document L2, it is helpful to building control bodies if such declarations are signed by someone who is suitably qualified, for example, a member of the Commissioning Specialists Association or the Commissioning Group of the Building and Engineering Services Association (B&ES) in respect of heating, ventilation and air-conditioning (HVAC) systems, or a member of the Lighting Industry Commissioning Scheme in respect of fixed internal or external lighting.
Where a building notice or full plans have been given to a local authority, the notice should be given within five days of the completion of the commissioning work; in other cases, for example where work is carried out by a person registered with a competent person scheme, it must be given within 30 days.
Where an approved inspector is the BCB, the notice should generally be given within five days of the completion of the building work. However, where the work is carried out by a person registered with a competent person scheme the notice must be given within 30 days. Where the installation of fixed building services which require commissioning is carried out by a person registered with a competent person scheme the notice of commissioning will be given by that person.
Until the BCB receives the notice of commissioning it may not be satisfied that Part L of the building regulations has been complied with and so is unlikely to issue a completion certificate.
[edit] Related articles on Designing Buildings Wiki
- Approved documents.
- Approved inspector.
- At your services - What to expect during commissioning.
- Building control body.
- Building regulations.
- Client commissioning.
- Commissioning documents.
- Commissioning plan.
- Commissioning planning.
- Commissioning v testing.
- Commissioning.
- Competent person schemes.
- Initial commissioning case studies.
- Seasonal and continuous commissioning.
- Set to work.
- Soft Landings.
- Specialist commissioning manager.
Featured articles and news
Types of domestic heating systems.
Will the way we heat homes change when winter comes ?
Extended reality in a post-pandemic world.
Can XR technology be leveraged in design & construction?
Or are you capping.
STEM ambassadors needed for ICE CityZen award.
Digital gaming competition for UK students aged 16 to 18.
Heritage protection in England vs Australia.
Fire doors and the Fire Door Inspection Scheme.
Three-quarters of fire doors fail inspections
UN International Day for Biological Diversity, May 22.
The role of geoparks, biospheres and world heritage sites.
BSRIA conference 2022, June 23.
Just one month to go ! Find out more here.
Restoring Broadbent’s Bath House
A new gallery for the University of Huddersfield.
Corruption in the construction industry.
What will it take to stop it ?
To celebrate world bee day 2022 !
Just one month until the changes to part L come into effect.
Not forgetting part F and the new part overheating part O.
Heat Pump demand rises by one quarter.
As energy prices jump up in cost.
With people in the UK from Ukraine.
Industry leader Steve Murray takes on role.
An abundant and versatile building material.
How overheating complicates ending gas in the UK.
600,000 heat pump installations targeted per year by 2028.
Cost planning, control and related articles on DB.
Helping prevent those unwanted outcomes.
ICE debate Public transport - post pandemic.
How has transport changed due to Covid-19 ?
Cross-ventilation in buildings. Do you have it ?
Will you need it ? after June 15 and the new Part O ?
Share your knowledge with the industry.
Create an account and write the first of many articles.