Non-compliant tender
This article describes in detail the tender process for a typical commercial construction contract.
For a wider description of the range of tender processes that might be adopted on different types of project, see Tender processes.
For more information about different contractual procurement routes, see Procurement route.
An invitation to tender will generally include very specific requirements for the information and format of the tender that prospective suppliers must submit. This ensures that necessary information is included and that it is in a format that the client is able to analyse and compare with other tenders.
If a prospective contractor or supplier submits a tender that does not comply with the client's requirements then that bidder is said to have submitted a non-compliant bid. This can result in the tender being rejected. Full compliance requires that all material conditions of the invitation to tender must be complied with.
A tender may be non-compliant by:
- Not answering all the question(s).
- Exceeding the required word length.
- Submitting in the wrong format e.g PDF when Excel or Word were required.
- Making a late submission.
- Not breaking down information in the correct way.
- Submitting proposals that do not comply with the client's requirements.
However, a non-compliant proposal, sometimes referred to as a variant bid, may be submitted intentionally if the tenderer believes that an alternative could offer better value for money that the requirements set out in the invitation to tender. However, non-compliant proposals should only be submitted if they have been requested or are explicitly permitted by the client, and they may need to be accompanied by a compliant bid to allow direct comparison with other tenders.
See also: Qualified bid.
[edit] Related articles on Designing Buildings Wiki
- Best value.
- Bid writer.
- Competitive tender.
- Contract award.
- Contract conditions.
- Contract documents.
- Due diligence when selecting contractors or subcontractors.
- Invitation to tender.
- Letter of award.
- Mid-tender interview.
- Most Economically Advantageous Tender (MEAT).
- Pre-tender interview.
- Procurement route.
- Qualified bid.
- Selection criteria.
- Tender documentation.
- Tender evaluation.
- Tender processes.
Featured articles and news
Villa Wolf in Gubin, history and reconstruction. Book review.
Construction contract awards down £1bn
Decline over the past two months compared to the same period last year, follows the positive start to the year.
Editor's broadbrush view on forms of electrical heating in context.
The pace of heating change; BSRIA market intelligence
Electric Dreams, Boiler Realities.
New President of ECA announced
Ruth Devine MBE becomes the 112th President of the Electrical Contractors Association.
New CIAT Professional Standards Competency Framework
Supercedes the 2019 Professional Standards Framework from 1 May 2025.
Difficult Sites: Architecture Against the Odds
Free exhibition at the RIBA Architecture Gallery until 31 May.
PPN 021: Payment Spot Checks in Public Sub-Contracts
Published following consultation and influence from ECA.
Designing Buildings reaches 20,000 articles
We take a look back at some of the stranger contributions.
Lessons learned from other industries.
The Buildings of the Malting Industry. Book review.
Conserving places with climate resilience in mind.
Combating burnout.
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.