Handover and close out
NB The 2020 edition of the RIBA Plan of Work has renamed this stage 'Handover'.
The process for completing the design and construction of a building is often divided into notional ‘stages’. This can be helpful in establishing milestones for the submission of progress reports, the preparation of information for approval, client gateways, and for making payments. However there is a great deal of ambiguity between the naming of stages by different organisations and the definition of what individual stages include (see comparison of work stages). As a result, it is important that appointment documents make it clear explicitly what activities fall within which stage, and what level of detail is required, rather than relying on rather vague stage names.
‘Handover and Close Out’ was a new phrase coined by the Royal Institute of British Architects (RIBA) for the 2013 Plan of Work. This plan comprised eight work stages, and its new terminology, stage referencing system and lack of detail have generated some criticism.
- 0 - Strategic definition.
- 1 - Preparation and brief.
- 2 - Concept design.
- 3 - Developed design.
- 4 - Technical design.
- 5 - Construction.
- 6 - Handover and close out.
- 7 - In use.
The RIBA states that Stage 6, Handover and Close Out maps broadly to the former Stage L: Post Practical Completion.
They describe the activities carried out during the stage as, ‘handover of building and conclusion of building contract’ including updating ‘as constructed’ information, commissioning, training and perhaps post-occupancy evaluation following the ‘soft landings’ process. Presumably the stage also includes tasks associated with the defects liability period and issuing the final certificate, although these are not described.
Previously, this stage might have been described as the ‘defects liability period’, the period which begins on certification of practical completion at the end of the construction stage and typically lasts six to twelve months, during which the client takes possession of the site, defects are rectified and then the final certificate issued. This is perhaps a better description of the stage and in the Designing Buildings Wiki project plans, we describe this stage as the ‘occupation and defects liability period’
The 2020 edition of the RIBA Plan of Work has renamed this stage 'Handover'.
[edit] Related articles on Designing Buildings Wiki
- Appointing consultants.
- BREEAM Handover.
- Comparison of work stages.
- Creating an asset register for construction projects.
- Defects liability period.
- Designing Buildings Wiki Project plans.
- Developed design.
- Handover to client.
- Migration strategy.
- RIBA Plan of Work.
- Soft landings.
- Traditional contract: occupation and defects liability period.
[edit] External references
Featured articles and news
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.
A carbon case for indigenous slate
UK slate can offer clear embodied carbon advantages.
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.