Extra over (EO)
‘Extra over’ (EO) is a term that is often used when taking off for a bill of quantities (BoQ). Taking off is the process of identifying elements of construction works that can be measured and priced.
When taking off for a BoQ, the term ‘extra over’ can be used to refer to items that to a certain extent have already been measured, but have not been priced at the full value of all their labour and materials. A common example of this is when measuring drain pipes, for which the estimator may determine a cost based on the full length of the pipe measured along its centre-line, and then assess an ‘extra over’ cost for the additional cost necessary to pay for fittings such as bends and junctions. So the cost of a section of pipe with a bend is the cost of the length of the pipe plus the extra over cost for the bend.
EO items should be listed directly beneath the main item over which they are measured, as this simplifies the the interpretation of the BoQ by suppliers. If the EO item cannot be listed immediately beneath, reference should be given in its description in the main item it relates to.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.






















Comments
good explanation