Extra over (EO)
‘Extra over’ (EO) is a term that is often used when taking off for a bill of quantities (BoQ). Taking off is the process of identifying elements of construction works that can be measured and priced.
When taking off for a BoQ, the term ‘extra over’ can be used to refer to items that to a certain extent have already been measured, but have not been priced at the full value of all their labour and materials. A common example of this is when measuring drain pipes, for which the estimator may determine a cost based on the full length of the pipe measured along its centre-line, and then assess an ‘extra over’ cost for the additional cost necessary to pay for fittings such as bends and junctions. So the cost of a section of pipe with a bend is the cost of the length of the pipe plus the extra over cost for the bend.
EO items should be listed directly beneath the main item over which they are measured, as this simplifies the the interpretation of the BoQ by suppliers. If the EO item cannot be listed immediately beneath, reference should be given in its description in the main item it relates to.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.
A carbon case for indigenous slate
UK slate can offer clear embodied carbon advantages.
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.






















Comments
good explanation