Extra over (EO)
‘Extra over’ (EO) is a term that is often used when taking off for a bill of quantities (BoQ). Taking off is the process of identifying elements of construction works that can be measured and priced.
When taking off for a BoQ, the term ‘extra over’ can be used to refer to items that to a certain extent have already been measured, but have not been priced at the full value of all their labour and materials. A common example of this is when measuring drain pipes, for which the estimator may determine a cost based on the full length of the pipe measured along its centre-line, and then assess an ‘extra over’ cost for the additional cost necessary to pay for fittings such as bends and junctions. So the cost of a section of pipe with a bend is the cost of the length of the pipe plus the extra over cost for the bend.
EO items should be listed directly beneath the main item over which they are measured, as this simplifies the the interpretation of the BoQ by suppliers. If the EO item cannot be listed immediately beneath, reference should be given in its description in the main item it relates to.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Comments
good explanation