Extension of time request
Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. In the United States, this is described as a time extension. The UK equivalent is an extension of time (EOT). Fore more information see: Extension of time.
Time extensions may be granted if the contractor can demonstrate that the delay was caused by events beyond their control. The contract will typically specify the circumstances and format in which a time extension request may be made.
A request will commonly include the following details:
- The delay that has been incurred and the affected activities.
- The specific issues that caused the delay.
- What steps have been taken to mitigate the delay.
- Schedule or cost adjustments that have been made to try and reduce the impact of the delay.
- The contract clause that allows the request.
- The amount of time being requested (in calendar days) and the proposed recovery plan.
- Supporting documents, such as; photographs, video footage, timesheets, and so on.
- Evidence of communications warning of possible delays.
In submitting the time extension request, the contractor must consider that calendar days are not the same as working days, that insurances and other bonds may need to be re-issued to cover any agreed extension period, and no further time will need to be requested relating to the same events.
If they approve the request, the project manager must reply by letter and issue a change order. The contract may specify a time frame within which time extension requests should be submitted and a response issued.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Recognition, influence and growth
SocEnv identifies three strategic pillars in new strategy to 2045.
Discover the future of roofing, cladding and insulation.
New guidance for professional practice, cultural change and regulation in social housing.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.

















