Excepted risk
Insurance provides third-party protection against risks. Risks on construction projects can be significant, and so insurance is very common, providing protection both for the insured, and for the party to whom the insured has a liability.
Many standard forms of construction contract include a requirement for insurance to be taken out by the parties to the contract. Policies may be taken out by the contractor or by the client depending on the form of contract and the options selected, but they will generally be in the form of a ‘joint names policy’ in the names of both the contractor and the client. This gives both parties their own rights to claim against the insurer. Other parties, such as funders may also be added as a joint name.
Insurance policies may cover all risks, or may be restricted to certain ‘specified perils.’ However, in either case, there may be ‘excepted risks’, for which insurance is not required (because it will usually be unobtainable).
Excepted risks might include:
- The use or occupation of the works by the employer, its agents, servants or contractors.
- Any fault, defect, error or omission in the design of the works (other than design provided by the contractor).
- Riot, war, invasion, act of foreign enemies or hostilities.
- Civil war, rebellion, revolution, insurrection or military or usurped power (not including terrorism).
- Radiation or contamination by radioactivity.
- Pressure waves caused by aircraft or other aerial devices travelling at sonic or supersonic speeds.
The cost of rectifying damage caused by such risks is generally borne by the employer, although there is usually provision for the apportionment of rectification costs where the cause is contributed to by both an excepted risk and one for which the contractor is responsible.
[edit] Related articles on Designing Buildings Wiki:
- Alternative Dispute Resolution legislation.
- Compensation event.
- Contract conditions.
- Cost reimbursable contract.
- Defect.
- Insurance.
- Joint names policy.
- Misrepresentation and insurance.
- Specified perils in construction contracts.
[edit] External references
- ‘Construction Insurance and UK Construction Contracts’ (2nd ed.), LEVINE, M., TER HAAR, R., Informa Law (2008)
Featured articles and news
50th Golden anniversary ECA Edmundson apprentice award
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Digital technology, transformation and cybersecurity
Supporting SMEs through Digitalisation in Construction.
Villa Wolf in Gubin, history and reconstruction. Book review.
Construction contract awards down one billion pounds
Decline over the past two months compared to the same period last year, follows the positive start to the year.
Editor's broadbrush view on forms of electrical heating in context.
The pace of heating change; BSRIA market intelligence
Electric Dreams, Boiler Realities.
New President of ECA announced
Ruth Devine MBE becomes the 112th President of the Electrical Contractors Association.
New CIAT Professional Standards Competency Framework
Supercedes the 2019 Professional Standards Framework from 1 May 2025.
Difficult Sites: Architecture Against the Odds
Free exhibition at the RIBA Architecture Gallery until 31 May.
PPN 021: Payment Spot Checks in Public Sub-Contracts
Published following consultation and influence from ECA.