The term ‘employer delay’ is commonly used to describe any delay caused by an employer risk event (an event or cause of delay or disruption which under the contract is at the risk and responsibility of the Employer).
The Society of Construction Law Delay and Disruption Protocol, 2nd edition, distinguishes between:
- Employer delay to progress, which is a delay that will merely cause delay to the contractor’s progress without causing a contract completion date to be missed.
- Employer delay to completion, which is a delay that will cause a contract completion date to be missed.
The expression 'excusable delay' is sometimes used to describe an employer delay in
respect of which the contractor is entitled to an extension of time.
Ref Society of Construction Law Delay and Disruption Protocol, 2nd edition, February 2017, published by the Society of Construction Law (UK). https://www.scl.org.uk/resources/delay-disruption-protocol
[edit] Related articles on Designing Buildings Wiki
- Building completion.
- Certificate of non completion.
- Completion.
- Completion date.
- Concurrent delay.
- Contract completion date.
- Contractor’s planned completion date.
- Delay.
- Delay to completion.
- Delay to progress.
- Extension of time.
- Loss and expense.
- Practical completion.
- Progress of construction works.
- Scheduling construction activities.
- Sectional completion.
- Time at large.
- Programme.
Featured articles and news
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
70+ experts appointed to public sector fire safety framework
The Fire Safety (FS2) Framework from LHC Procurement.
Project and programme management codes of practice
CIOB publications for built environment professionals.
The ECA Industry Awards 2024 now open !
Recognising the best in the electrotechnical industry.
Sustainable development concepts decade by decade.
The regenerative structural engineer
A call for design that will repair the natural world.
Buildings that mimic the restorative aspects found in nature.
CIAT publishes Principal Designer Competency Framework
For those considering applying for registration as a PD.
BSRIA Building Reg's guidance: The second staircase
An overview focusing on aspects which most affect the building services industry.
Design codes and pattern books
Harmonious proportions and golden sections.
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding..