Element unit rate
The New Rules of Measurement (NRM) are published by the Royal Institute of Chartered Surveyors (RICS). They provide a standard set of measurement rules for estimating, cost planning, procurement and whole-life costing for construction projects.
According to NRM1: Order of cost estimating and cost planning for capital building work, the term 'element' refers to:
'...a major part of a group element (e.g. the elements that create group element 3:
Internal finishes are 3.1: Wall finishes, 3.2: Floor finishes, and 3.3: Ceiling finishes).'
The term ‘element unit rate’ (EUR) means:
‘…the total cost of an element divided by the element unit quantity (EUQ). For example, the EUR for external walls is the total cost of the external walls divided by EUQ for external walls. EURs include all the cost of all materials, labour, plant, subcontractor’s preliminaries, subcontractor’s design fees and subcontractor’s overheads and profit. EURs exclude main contractor’s preliminaries, main contractor’s overheads and profit and other allowances, such as project/design team fees, other development/project costs, risk allowances and inflation. These items are to be assessed separately.’
Where, the ‘element unit quantity’ (EUQ) is:
‘…a unit of measurement that relates solely to the quantity of the element or sub-element itself (e.g. the area of the external walls, the area of windows and external doors and the number of internal doors).’
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Editor's broadbrush view on forms of electrical heating in context.
The pace of heating change; BSRIA market intelligence
Electric Dreams, Boiler Realities.
New President of ECA announced
Ruth Devine MBE becomes the 112th President of the Electrical Contractors Association.
New CIAT Professional Standards Competency Framework
Supercedes the 2019 Professional Standards Framework from 1 May 2025.
Difficult Sites: Architecture Against the Odds
Free exhibition at the RIBA Architecture Gallery until 31 May.
PPN 021: Payment Spot Checks in Public Sub-Contracts
Published following consultation and influence from ECA.
Designing Buildings reaches 20,000 articles
We take a look back at some of the stranger contributions.
Lessons learned from other industries.
The Buildings of the Malting Industry. Book review.
Conserving places with climate resilience in mind.
Combating burnout.
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.