Door clear opening width
Approved document M, ‘Access to and use of buildings', requires that a minimum clear width is provided by door openings.
According to the approved document, the effective clear width of a door ‘…is the width of the opening measured at right angles to the wall in which the door is situated from the outside of the door stop on the door closing side to any obstruction on the hinge side, whether this be projecting door opening furniture, a weather board, the door or the door stop’
The minimum allowable clear opening widths for dwellings are set out below:
Doorway clear opening width (mm) | Corridor clear passageway width (mm) |
750 or wider | 900 (when approached head on) |
750 | 1200 (when approach is not head-on) |
775 | 1050 (when approach is not head-on) |
800 | 900 (when approach is not head on) |
For buildings other than dwellings, the minimum allowable clear opening widths are:
Direction and width of approach | New buildings (mm) | Existing buildings (mm) |
Straight-on | 800 | 750 |
At right angles to an access route at least 1,500 mm wide | 800 | 750 |
At right angles to an access route at least 1,200 mm wide | 825 | 775 |
External doors to buildings used by the general public. | 1000 | 775 |
The clear opening width can be calculated as:
- The width of the door leaf.
- Plus the gap between the leading edge of the door and the frame when the door is closed.
- Minus the width of the door stop at the leading edge of the door.
- Minus the thickness of the door leaf (or the door stop if that is wider).
- Minus the width of any obstructing door furniture (such as the door handle) that projects into the opening when the door is open. If the door opens to more than 90°, door furniture may not obstruct the clear opening width.
Unless a door is powered, there must be a 300 mm nib beyond the leading edge of the door to allow wheelchair users to properly access the handle.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
Welsh Recharging Electrical Skills Charter progresses
ECA progressing on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.