Deed of variation
A deed of variation can be used to formally change the terms of an existing contract. It is used when the parties involved - typically the client and the contractor - agree to alter specific provisions of their original contract after it has been executed. The deed ensures these changes are legally binding and properly documented, avoiding misunderstandings or disputes in the future. It helps maintain the integrity and continuity of the contractual relationship while allowing for necessary flexibility during the construction process.
Changes can include adjustments to the project schedule, costs, specifications, payment terms, or any other contractual obligations that need to be altered due to various reasons, such as unforeseen circumstances or mutual agreement to improve project outcomes.
All parties to the original contract must agree to the changes, and the deed must be signed by these parties to be legally effective. As a deed, it requires a higher level of formality than a simple contract variation. This often includes the need for witnessing signatures and sometimes the use of a company seal.
It should clearly state the specific clauses being amended and detail the new terms replacing the original ones. This helps maintain clarity and enforceability. It is often advisable to seek legal advice when drafting or agreeing to a deed of variation to ensure that all implications are fully understood and that the deed is correctly executed.
[edit] Related articles on Designing Buildings
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.