Consequential improvements in construction
Consequential improvements refer to energy efficiency improvements that are consequential to changes to a building, which are required by regulation 28 of the Building Regulations (guidance for which appears in Section 6 of Approved document L2B: Conservation of fuel and power in existing buildings other than dwellings) to make the whole building comply with Part L of the Building Regulations
The regulation relates to proposed works to existing buildings (other than dwellings) with a total useful floor area of over 1000m2, and include:
- An extension.
- Installation of new fixed building services (other than renewable energy generators).
- Increasing the capacity of fixed building services (other than renewable energy generators).
Where such works are proposed, additional consequential improvements will be required to the extent that the necessary improvements are technically, functionally and economically feasible.
In most circumstances, this means that the payback period for the consequential improvements required does not exceed 15 years (or less if the expected life of the building is less than 15 years).
Consequential improvements could include:
- Upgrading heating, cooling or air handling systems.
- Upgrading lighting systems.
- Installing energy metering.
- Upgrading thermal elements.
- Replacing windows.
- On-site energy generation.
- Applying measures proposed in a recommendations report accompanying an Energy Performance Certificate.
In the case of an extension, the regulation can be complied with if the value of consequential improvements is not less than 10% of the value of the principal works.
In the case of changes to fixed building services, the building fabric should be improved so that the energy consumption of the services is not excessive, and additional consequential improvements must be made as described in the list above. Improvements to the building fabric in this case do not count towards the value of the consequential improvements. NB This does not apply if the services capacity is increased to supply a new extension rather than to improve services to an exiting space.
For changes to fixed building services, improvements to the building fabric are considered technically, functionally and economically feasible where the existing thermal elements have a U-value lower than those set out in the approved document. In the case of cooling, both the U-values of thermal elements and the solar gains of windows are set out, and in the case of lighting, an effective lamp efficacy is set.
Once the works are complete, the building owner should be provided with sufficient information to operate the building efficiently. This can be done by preparing a building log book.
NB Proposals to extend requirements for consequential improvements to dwellings (as part of the introduction of the green deal) were finally dropped by Communities Secretary Eric Pickles at the end of 2012.
[edit] Related articles on Designing Buildings
- Building log book.
- Building Regulations.
- Energy efficiency of traditional buildings.
- Energy performance certificates.
- Energy targets.
- Environmental plan.
- Green Deal.
- Principal works.
- Sustainability.
- U-Value.
[edit] External references
- Approved document L2B: Conservation of fuel and power in existing buildings other than dwellings.
Featured articles and news
New President of ECA announced
Ruth Devine MBE becomes the 112th President of the Electrical Contractors Association.
New CIAT Professional Standards Competency Framework
Supercedes the 2019 Professional Standards Framework from 1 May 2025.
Difficult Sites: Architecture Against the Odds
Free exhibition at the RIBA Architecture Gallery until 31 May.
PPN 021: Payment Spot Checks in Public Sub-Contracts
Published following consultation and influence from ECA.
Designing Buildings reaches 20,000 articles
We take a look back at some of the stranger contributions.
Lessons learned from other industries.
The Buildings of the Malting Industry. Book review.
Conserving places with climate resilience in mind.
Combating burnout.
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.