Consent to spend
Contents |
[edit] Introduction
In construction the term 'consent to spend' is sometimes referred to as an ‘if’ contract. A letter with instructions to proceed and consent to spend allows work to proceed up to a certain value while the contract itself is still being drafted. The consent to spend letter can be a legally binding contract that pre-dates the principal contract. Once the principal contract is signed the consent to spend letter can be superseded. Consent to spend can also be captured in a letter of intent.
[edit] Consent to spend letter contents
It is good practice to capture as a minimum the following items in a consent to spend letter:
- The parties involved in the contract.
- A description of the works required to avoid ambiguity.
- A statement of the intention of the parties to enter into a formal contract.
- The price, or if the price is not known, established rates can be mentioned or the contract administrator can detail specific requirements to ensure financial control.
- The maximum expenditure limit relating to the consent to spend contract.
- The date of possession and access to site.
- The completion date if known.
- The contract administrator can refer to a short-term program.
- There might be sectional completion requirements that can be listed.
- Insurance requirements.
- Termination procedure.
- Confirmation that the contract created by the consent to spend will be terminated by the principle contract.
It is advisable to capture as much detail as possible in the letter of consent to spend. The letter can be a great advantage to the construction program, but the risk of not capturing details or covering basic clauses can result in problems.
[edit] An alternative to a consent to spend or letter of intent
An employer can use a pre-construction service agreement (PCSA) if they need the input of a contractor before the construction contract is in place. A pre-construction service agreement is a contract commonly used in two-stage tendering. Two stage tendering involves the employer tendering the project on the basis of an incomplete design. A contractor is then chosen to work with the employer based on its proposal for the pre-construction second stage of the tender.
The employer might want the contractor’s input on programming, designs and buildability prior to issuing the construction contract. In the right circumstances, a PCSA can be beneficial to both parties and bring design improvements and costs savings, and encourage a strong working relationship. A letter of intent/consent to spend is not likely to achieve the same benefits as a PCSA. A PCSA is however a formal agreement and a small-scale project might not have the budget or program to accommodate this type of formal agreement.
[edit] Conclusion
A consent to spend letter can be a good tool to expedite work on site but contract administrators need to be aware of the legal implications to avoid unnecessary risk to the project.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.