Calculating compensation for property damage
Where works carried out on one property damage another, should compensation be payable on the basis of reinstatement costs or diminution in value? The High Court tackled that issue recently in the case of Lea Valley Developments Limited v Derbyshire.
The owner of a house had obtained an award under the Party Wall etc. Act 1996 that authorised a building project, including excavation works. The award required the owner to make good any decorative or structural damage caused to a neighbouring property, a block of flats, or to make payment in lieu.
The works caused damage to the block that was agreed to be so serious that it was beyond economic repair. The costs of demolishing and rebuilding the block were estimated at between £1 million and £2 million.
However, the house owner said that the diminution in the block’s value arising from the damage was between £500,000 and £1 million. The owners of both properties sought declarations as to the correct basis on which compensation was payable.
The Court rejected the owner of the block’s arguments that, on a true reading of the Act and the terms of the party wall award, there was no issue to be tried and that damages had to be calculated on a reinstatement basis. However, it also refused to grant the owner of the house a declaration that, as a matter of common law, the diminution in value basis necessarily prevailed.
The issue of whether reinstatement or diminution in value represented the correct approach to the assessment of damages was highly fact sensitive and dependent on a wide range of factors. There was no rule of law that prohibited awards on either basis or that required one to prevail over the other. It was thus inappropriate to resolve the issue without hearing detailed factual evidence.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.