Bill of quantities v Schedule of rates
Contents |
[edit] Introduction
This article explains the difference between a bill of quantities (BoQ) or a schedule of rates on construction projects. Both can be used to obtain prices from contractors and for valuing variations. The decision about whether to use a bill of quantities or a schedule of rates depends on the nature of the project as well as the chosen procurement route.
[edit] What is a bill of quantities?
A bill of quantities is a document prepared by the cost consultant (often a quantity surveyor) that provides project specific measured quantities of the items of work identified by the drawings and specifications in the tender documentation.
The bill of quantities is issued to tenderers for them to prepare a price for carrying out the works. The bill of quantities assists tenderers in the calculation of construction costs for their tender, and, as it means all tendering contractors will be pricing the same quantities (rather than taking off quantities from the drawings and specifications themselves), it also provides a fair and accurate system for tendering.
The contractor tenders against the bill of quantities, stating their price for each item. This priced bill of quantities constitutes the tenderer's offer.
Typically a bill of quantities will be appropriate on projects that have been designed in detail, and so the precise quantities required are known.
For more information see: Bill of quantities.
[edit] What is a schedule of rates?
A schedule of rates is a list in a contract setting out the staff, labour and plant hire rates that the contractor will use for pricing cost reimbursable instructed daywork. It does not contain any quantities for the specific work items and is typically used when the nature of work required is known but it cannot be quantified, or if continuity of programme cannot be determined.
On a much larger scale, a similar process might be used on a 'schedule of rates term contract', 'term contract' or 'measured term contract'. Tenderers quote unit rates against a document that is intended to cover all likely activities that might form part of the works. As the extent of the work is unknown, the unit rates include overheads and profit. General preliminaries such as scaffolding, temporary power, supervision and temporary accommodation will also have rates. On projects longer than around 18 months there might be escalation provisions based on annual percentage increases.
For more information see: Schedule of rates.
[edit] Summary
In summary, a bill of quantities will typically be used when a detailed design has been prepared and precise quantities can be calculated, whereas a schedule of rates will be used when quantities cannot be determined.
[edit] Related articles on Designing Buildings
Featured articles and news
Key points for construction at a glance with industry reactions.
Functionality, visibility and sustainability
The simpler approach to specification.
Architects, architecture, buildings, and inspiration in film
The close ties between makers and the movies, with our long list of suggested viewing.
SELECT three-point plan for action issued to MSPs
Call for Scottish regulation, green skills and recognition of electrotechnical industry as part of a manifesto for Scottish Parliamentary elections.
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.