Trade contractor
On construction management contracts, a construction manager is appointed on a consultancy and management basis to provide advice to the client during the pre-construction stages and then to manage the construction of the works. The works are divided into packages which are contracted to separate contractors. These contractors are referred to as trade contractors rather than sub-contractors (as they are contracted directly by the client, rather than being sub-contracted to the construction manager). The separate appointment of trade contractors should reduce the cost of contracts, as the management element is being provided by the construction manager. It also allows the advancement of some works (such as groundworks or piling) which might begin even before design of the above-ground works is complete.
Characteristics of trade contracts include:
- Trade contractors may be appointed through a single-stage procurement process, or through a two-stage process with a pre-construction services agreement for the first stage.
- Each trade contract must have its own separate practical completion certification and so they may have different defects liability periods. Certification cannot be dependent on completion of works outside of the scope of the contract. As trade contracts may be completed at different times, the construction manager must ensure that measures are in place to protect completed work from ongoing activities.
- Trade contracts (such as the Joint Contracts Tribunal (JCT) CM/TC 2011) do not include provisions for liquidated damages, instead the trade contractor indemnifies the client's direct loss and/or expense for lateness.
- Trade contracts may allow for retention, or may include a requirement for a retention bond.
- Trade contracts should include requirements to adopt collaborative practices.
- As there is no main contractor, trade contractors should provide master programmes for their works.
- Trade contractors should be required to provide regular information in relation to key performance indicators.
- Where they carry out design, trade contractors may be required to provide as-built drawings.
Notes
- On management contracts, contractors are known as 'works contractors'.
- For a detailed description of the sequence of tasks necessary on a construction management contract, see the work plan: construction management: outline work plan.
NB A trades contractor (with an 's') is a more general term which simply refers to a contractor who undertakes a particular class of construction work, such electrical installation. See Trades contractor for more information.
[edit] Related articles on Designing Buildings
- Back-to-back provisions in construction contacts.
- Collaborative practices.
- Collateral warranties.
- Construction manager.
- Construction contract.
- Contracting.
- Contractor.
- Contractors master programme.
- Main contractor.
- Management contract.
- Operative.
- Procurement route.
- Sub-agent.
- Sub-contractor.
- Trade body.
- Types of contractor.
- Works contractor.
Featured articles and news
Classroom electrician courses a 'waste of money'
Say experts from the Electrical Contractors’ Association.
Wellbeing in Buildings TG 10/2025
BSRIA topic guide updates.
With brief background and WELL v2™.
From studies, to books to a new project, with founder Emma Walshaw.
Types of drawings for building design
Still one of the most popular articles the A-Z of drawings.
Who, or What Does the Building Safety Act Apply To?
From compliance to competence in brief.
The remarkable story of a Highland architect.
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.