Reserved matters in planning permissions
Outline planning applications can be used to find out whether a proposed development is likely to be approved by the planning authority, before substantial costs are incurred developing a detailed design.
Outline planning applications allow the submission of outline proposals, the details of which may be agreed as 'reserved matters' applications at a later stage.
On 10 August 2006, changes to the outline planning permission process came into force intended to make outline planning applications more 'detailed' and so to restrict the extent of reserved matters.
Reserved matters that might be the subject of further applications once outline planning consent has been obtained can now include:
- The layout of buildings within the proposed development.
- The precise height, width and length of individual buildings.
- The appearance of buildings.
- Access to and within the site for vehicles, cycles and pedestrians.
- Landscape proposals.
The details of the reserved matters application must be in line with the outline approval, including any conditions attached to the permission. It may be necessary to reapply for outline or full planning permission if the proposals have changed in any way.
Outline permission is not a permission to start work on site. The permission notice will state which matters have been reserved for later approval. When all of the reserved matters have been approved, work may begin on the site.
Reserved matters applications should be submitted within 3 years of outline permission being granted.
Outline planning permission lasts for two years from the date reserved matters were approved, or three years from the date of the outline planning permission, whichever is the later.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing with 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
Comments
If a reserved matters application in respect of a new road junction from a possible new housing development onto the main highway is unsupported by Highways England, on the grounds of unachievable visibility splay distances, must the Local Authority then turn down that application? What then happens to the original planning application for that access road, which was previously approved?