Suspension of performance in construction contracts
Construction contracts will generally require that the contractor progresses the works regularly and diligently. There is no common law right that allows suspension of performance of the works, however, there are contractual and statutory provisions under which the contractor may suspend performance.
The Housing Grants, Construction and Regeneration Act 1996 is intended to ensure (amongst other things) that payments are made promptly throughout the supply chain. Its provisions include:
- The right to be paid in interim, periodic or stage payments.
- The right to be informed of the amount due, or any amounts to be withheld.
- The right to suspend performance for non-payment.
The Act applies to all contracts for 'construction operations', including construction contracts and consultants’ appointments.
Following the 2011 amendments to the Act, parties have the right to suspend performance of any or all contractual obligations when a required payment of a notified sum has not been made. This includes, suspension of part or all of the works, but also other contractual obligations such as the provision of insurance. They will also be entitled to payment for reasonable costs incurred in exercising their right to suspend performance, and to have the period of suspension (and any consequential periods) disregarded when calculating the competition date.
The right to suspend only in relates to the contract for which payment has not been made and the party must not suspend statutory duties. Seven days notice must be given of the intention to suspend performance and the right ceases if the payment is made.
In some forms of construction contract, such as JCT contracts, there are also express terms allowing suspension for failure to make a payment by the due date. There may also be other circumstances in which the contract allow suspension of the works. Clauses dealing with suspension tend to be similar in nature to those dealing with termination. In addition, there may be a right to terminate at end of the period of suspension or if the suspension becomes prolonged, with no prospect of re-commencing.
Suspension may be permitted due to a breach of contract by the employer, the employer becoming insolvent, as a result of force majeure, or by agreement between the parties, for example if circumstances make proceeding with the works temporarily impossible, if there are difficulties in determining how to proceed with a project or if the client has difficulty in raising funds to pay for the work to proceed at the speed anticipated by the contract.
The provisions of extension of time clauses also allow the construction period to be extended where there are delays that are not the contractor's fault. For more information, see extension of time.
It is important to be certain that the circumstances do allow the works to be suspended, and that the correct procedures are being followed. If the employer has exercised some right under the contract to withhold or reduce payment, then wrongfully suspending the works could possibly amount to a repudiatory breach, where one party behaves in such a way that it indicates it no longer intends to accept its obligations under the contract, allowing the innocent party to terminate the contract and to sue for damages. However, in Mayhaven Healthcare Ltd vs Bothma it was found that this is not automatically the case.
The complexity of the situation means it may be necessary to obtain legal advice before suspending performance.
[edit] Related articles in Designing Buildings Wiki
- Breach of contract.
- Extension of time.
- Force majeure.
- Frustration.
- Housing Grants, Construction and Regeneration Act .
- Insolvency.
- Performance.
- Termination.
[edit] External references
- BAILII: Mayhaven Healthcare Ltd vs Bothma.
Featured articles and news
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.