Suspension of performance in construction contracts
Construction contracts will generally require that the contractor progresses the works regularly and diligently. There is no common law right that allows suspension of performance of the works, however, there are contractual and statutory provisions under which the contractor may suspend performance.
The Housing Grants, Construction and Regeneration Act 1996 is intended to ensure (amongst other things) that payments are made promptly throughout the supply chain. Its provisions include:
- The right to be paid in interim, periodic or stage payments.
- The right to be informed of the amount due, or any amounts to be withheld.
- The right to suspend performance for non-payment.
The Act applies to all contracts for 'construction operations', including construction contracts and consultants’ appointments.
Following the 2011 amendments to the Act, parties have the right to suspend performance of any or all contractual obligations when a required payment of a notified sum has not been made. This includes, suspension of part or all of the works, but also other contractual obligations such as the provision of insurance. They will also be entitled to payment for reasonable costs incurred in exercising their right to suspend performance, and to have the period of suspension (and any consequential periods) disregarded when calculating the competition date.
The right to suspend only in relates to the contract for which payment has not been made and the party must not suspend statutory duties. Seven days notice must be given of the intention to suspend performance and the right ceases if the payment is made.
In some forms of construction contract, such as JCT contracts, there are also express terms allowing suspension for failure to make a payment by the due date. There may also be other circumstances in which the contract allow suspension of the works. Clauses dealing with suspension tend to be similar in nature to those dealing with termination. In addition, there may be a right to terminate at end of the period of suspension or if the suspension becomes prolonged, with no prospect of re-commencing.
Suspension may be permitted due to a breach of contract by the employer, the employer becoming insolvent, as a result of force majeure, or by agreement between the parties, for example if circumstances make proceeding with the works temporarily impossible, if there are difficulties in determining how to proceed with a project or if the client has difficulty in raising funds to pay for the work to proceed at the speed anticipated by the contract.
The provisions of extension of time clauses also allow the construction period to be extended where there are delays that are not the contractor's fault. For more information, see extension of time.
It is important to be certain that the circumstances do allow the works to be suspended, and that the correct procedures are being followed. If the employer has exercised some right under the contract to withhold or reduce payment, then wrongfully suspending the works could possibly amount to a repudiatory breach, where one party behaves in such a way that it indicates it no longer intends to accept its obligations under the contract, allowing the innocent party to terminate the contract and to sue for damages. However, in Mayhaven Healthcare Ltd vs Bothma it was found that this is not automatically the case.
The complexity of the situation means it may be necessary to obtain legal advice before suspending performance.
[edit] Related articles in Designing Buildings Wiki
- Breach of contract.
- Extension of time.
- Force majeure.
- Frustration.
- Housing Grants, Construction and Regeneration Act .
- Insolvency.
- Performance.
- Termination.
[edit] External references
- BAILII: Mayhaven Healthcare Ltd vs Bothma.
Featured articles and news
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.