Rubble trench foundation
This is a variation of the trench fill foundation, and is a traditional construction method which uses loose stone or rubble to minimise the concrete requirement and improve drainage. It follows the same approach as a French drain, with a trench that is filled with crushed stone letting any water drain down and away from the foundation.
This approach has been used in various guises for thousands of years but it was popularised in the 20th century by the architect Frank Lloyd Wright, and has been promoted as being more environmentally-friendly than other foundation types.
The bottom of the trench should slope with an even descent of at least 3 cm for every 1 m of trench, which diverts the water towards one point, from which it can be diverted away through an outlet or to a dry well.
The trench should be lined with a geotextile material to prevent the surrounding soil from clogging up the trench and outlet. It is then filled with angular and washed stones of average size 2.5-5 cm, with them being compacted at every 30 cm layer using either a pneumatic or hand-powered tamper.
The washing of the crushed stone is important since it removes sand, silt and other small particles that could build up in the trench over time.
When it reaches around 20-30 cm below grade, the larger blocks of stone can begin to be built up as a continuous wall.
This type of trench is unsuitable for particularly expansive or poor load-bearing soils. An alternative, less eco-friendly solution, is to combine the rubble fill with a concrete grade beam.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Your views needed - a strategy for the professions, trades and occupations.
Confronting competency, codes, capacity and costs.
The hidden risk in modern construction supply chains.
Construction Management, 10 June
24 months to 14: CITB launches accelerated apprenticeships.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.
Construction Management, 10 June.
Heat pumps beat boilers in new home tests.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.