Pioneer Cladding Limited v John Graham Construction Limited
Contents |
[edit] Introduction
This is another case of an impecunious party in an adjudication seeking to enforce payment but the opposing party successfully securing a stay of enforcement. Previous cases concerning a stay of execution of an adjudicator’s award have been covered in Westshield v Buckingham 2013 and FG Skerritt Ltd v Caledonian Building Systems Ltd 2013. Here though, interesting points emerged from due diligence inquiries made by the contractor before appointing the subcontractor.
[edit] Background
John Graham Construction, the defendant contractor (“Graham”), engaged Pioneer Cladding, the claimant subcontractor (“Pioneer”), in June 2011 for cladding and curtain walling works at a site in South Shields.
A dispute arose under the subcontract which Pioneer successfully referred to adjudication. It was awarded approximately £193,000 and began enforcement proceedings to which Graham sought a stay of execution based on Pioneer’s financial circumstances.
The matter came before Mr Justice Coulson in the Technology and Construction Court (TCC) who reiterated the principles in deciding whether to grant a stay, including:
- The inability of the claimant to repay the judgment sum in subsequent proceedings.
- That a stay will usually be granted if the claimant is insolvent.
- If the claimant’s present financial position is weak that would not usually justify a stay if the claimant’s financial circumstances were similar to its circumstances at the time the contract was made and the claimant’s financial situation is due to the defendant’s non payment of the adjudicator’s award.
On the evidence, the court found that Pioneer would be unable to repay the outstanding sum in subsequent proceedings.
Interesting findings emerged in response to whether Pioneer’s financial position was similar to that at the time the parties contracted. Two firms were nominated by the employer for the cladding subcontract: Baris and Pioneer. Graham had undertaken detailed checks to investigate the financial position of the front-runner, Pioneer and had been concerned by the results thrown up by its investigations. Searches revealed the company had not traded and conflicting accounts given as to the company’s turnover. Baris contacted Graham to inform it that Pioneer had gone into administration the previous year. Naturally Graham was concerned by such news, so much so that it convened a meeting with Pioneer’s director to discuss the issue. The director painted a rosy picture of Pioneer’s finances in terms of its turnover and order book. Luckily for Graham, its director took contemporaneous notes of the meeting with his counterpart: this is music to a lawyer’s ears and demonstrates the importance of keeping good written records. It was that contemporaneous note that would prove significant in Graham’s evidence.
[edit] The court’s findings
The judge found that Pioneer’s director had misled Graham into thinking that its financial position was better than it in fact was. It further decided that on the basis of these assurances and following criticism of Baris’s unprofessional conduct from the project architect, Graham was influenced to engage Pioneer as its cladding subcontractor.
This was not a case where a party knew of its counterparty’s poor financial situation at the time of subcontracting so cannot now argue this as a reason to stay enforcement of an adjudicator’s award. Neither could it be said that Pioneer’s impecuniosity was due to the non payment of the adjudicator’s award. The stay was granted due to Pioneer’s actions in misleading Graham into thinking it was financially sound thereby inducing it to contract on a false premise. The court granted a stay of the enforcement proceedings in Graham’s favour pending the outcome of the arbitration.
[edit] Conclusion
This case is a useful reminder of the importance of undertaking background financial checks before deciding who to contract with. In the current economic climate, comprehensive and thorough checks are vital, both as a risk management tool and to provide a level of assurance as to the financial viability of a fellow contracting party in meeting its contractual obligations. The law will not assist parties contracting with financially weak companies which they knew about at the time of contract. Graham’s saving grace was that it had plainly done its homework in performing the necessary checks but was ultimately misled.
Maintaining good written records is a must.
This article was created by construction lawyer --Najma Dunnett as part of an ongoing series of legal articles. Follow Najma on Twitter to keep up to date with the latest changes in construction law @NDunnett_Cons.
[edit] Related articles on Designing Buildings Wiki
- Due diligence when selecting contractors or subcontractors.
- FG Skerritt Ltd v Caledonian Building Systems Ltd 2013.
- Westshield v Buckingham 2013.
[edit] External references
- BAILII, The decision in full.
Featured articles and news
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.
A carbon case for indigenous slate
UK slate can offer clear embodied carbon advantages.
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.



















