Pioneer Cladding Limited v John Graham Construction Limited
Contents |
[edit] Introduction
This is another case of an impecunious party in an adjudication seeking to enforce payment but the opposing party successfully securing a stay of enforcement. Previous cases concerning a stay of execution of an adjudicator’s award have been covered in Westshield v Buckingham 2013 and FG Skerritt Ltd v Caledonian Building Systems Ltd 2013. Here though, interesting points emerged from due diligence inquiries made by the contractor before appointing the subcontractor.
[edit] Background
John Graham Construction, the defendant contractor (“Graham”), engaged Pioneer Cladding, the claimant subcontractor (“Pioneer”), in June 2011 for cladding and curtain walling works at a site in South Shields.
A dispute arose under the subcontract which Pioneer successfully referred to adjudication. It was awarded approximately £193,000 and began enforcement proceedings to which Graham sought a stay of execution based on Pioneer’s financial circumstances.
The matter came before Mr Justice Coulson in the Technology and Construction Court (TCC) who reiterated the principles in deciding whether to grant a stay, including:
- The inability of the claimant to repay the judgment sum in subsequent proceedings.
- That a stay will usually be granted if the claimant is insolvent.
- If the claimant’s present financial position is weak that would not usually justify a stay if the claimant’s financial circumstances were similar to its circumstances at the time the contract was made and the claimant’s financial situation is due to the defendant’s non payment of the adjudicator’s award.
On the evidence, the court found that Pioneer would be unable to repay the outstanding sum in subsequent proceedings.
Interesting findings emerged in response to whether Pioneer’s financial position was similar to that at the time the parties contracted. Two firms were nominated by the employer for the cladding subcontract: Baris and Pioneer. Graham had undertaken detailed checks to investigate the financial position of the front-runner, Pioneer and had been concerned by the results thrown up by its investigations. Searches revealed the company had not traded and conflicting accounts given as to the company’s turnover. Baris contacted Graham to inform it that Pioneer had gone into administration the previous year. Naturally Graham was concerned by such news, so much so that it convened a meeting with Pioneer’s director to discuss the issue. The director painted a rosy picture of Pioneer’s finances in terms of its turnover and order book. Luckily for Graham, its director took contemporaneous notes of the meeting with his counterpart: this is music to a lawyer’s ears and demonstrates the importance of keeping good written records. It was that contemporaneous note that would prove significant in Graham’s evidence.
[edit] The court’s findings
The judge found that Pioneer’s director had misled Graham into thinking that its financial position was better than it in fact was. It further decided that on the basis of these assurances and following criticism of Baris’s unprofessional conduct from the project architect, Graham was influenced to engage Pioneer as its cladding subcontractor.
This was not a case where a party knew of its counterparty’s poor financial situation at the time of subcontracting so cannot now argue this as a reason to stay enforcement of an adjudicator’s award. Neither could it be said that Pioneer’s impecuniosity was due to the non payment of the adjudicator’s award. The stay was granted due to Pioneer’s actions in misleading Graham into thinking it was financially sound thereby inducing it to contract on a false premise. The court granted a stay of the enforcement proceedings in Graham’s favour pending the outcome of the arbitration.
[edit] Conclusion
This case is a useful reminder of the importance of undertaking background financial checks before deciding who to contract with. In the current economic climate, comprehensive and thorough checks are vital, both as a risk management tool and to provide a level of assurance as to the financial viability of a fellow contracting party in meeting its contractual obligations. The law will not assist parties contracting with financially weak companies which they knew about at the time of contract. Graham’s saving grace was that it had plainly done its homework in performing the necessary checks but was ultimately misled.
Maintaining good written records is a must.
This article was created by construction lawyer --Najma Dunnett as part of an ongoing series of legal articles. Follow Najma on Twitter to keep up to date with the latest changes in construction law @NDunnett_Cons.
[edit] Related articles on Designing Buildings Wiki
- Due diligence when selecting contractors or subcontractors.
- FG Skerritt Ltd v Caledonian Building Systems Ltd 2013.
- Westshield v Buckingham 2013.
[edit] External references
- BAILII, The decision in full.
Featured articles and news
A case study and a warning to would-be developers
Creating four dwellings for people to come home to... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
























