FG Skerritt Ltd v Caledonian Building Systems Ltd
FG Skerritt Ltd v Caledonian Building Systems Ltd [2013] EWHC 1898 (TCC)
The 2013 case of Westshield v Buckingham related to the provision by Westshield Ltd of a guarantee to provide security for repayment of sums that may be due from Westshield Civil Engineering Ltd to Buckingham Group in subsequent proceedings and that that might have persuaded the court not to grant a stay of execution against Westshield.
In the case of FG Skerritt v Caledonian Building Systems, a similar situation arose in that the claimant, FG Skerritt became insolvent but a stay of execution contended for by the defendant, Caledonian Building Systems Ltd, was refused on the basis of the provision of a parent company guarantee by the claimant.
The defendant (the main contractor) engaged the claimant as its subcontractor to design and build the mechanical and electrical systems on a prison project. The form of subcontract was the DOM2 standard form dated 22 May 2009 with a contract price of £1.8m.
A dispute arose concerning the claimant’s invoice which the defendant refused to pay. The claimant subsequently went into administrative receivership but issued an adjudication notice claiming payment of approximately £214,000 due under invoices issued under the subcontract.
The adjudicator awarded the claimant full payment of its outstanding invoices in the sum of approximately £185,000 and noted the defendant had not served a withholding notice. The defendant wished to counterclaim for the costs of completion of the works and rectification of defects which could not be set off against the claimant.
The proceedings before the Technology and Construction Court (TCC) related to a summary judgment application by the claimant to enforce the adjudicator’s award. The defendant sought a stay of execution of the award on the basis of the claimant’s insolvency and possibility it may not be able to repay sums in subsequent proceedings. One of the issues raised by the defendant was the financial status of the claimant’s parent company MGL in providing a guarantee to avoid granting a stay of execution of the adjudicator’s award.
In respect of the court’s decision as to whether to grant a stay, reference was made by the defendant to the Insolvency Rules 1986 where the defendant submitted that due to the claimant’s insolvency and the defendant’s various counterclaims against it, summary judgment should be refused so that the counterclaims could be dealt with in the liquidation process (Note from Westshield v Buckingham, the factors the court will assess in deciding whether to grant a stay and that where a company is in liquidation a stay is usually granted due to the probable inability of that company to repay sums). The claimant submitted, however, that given its insolvency the matter could be dealt with and summary judgment granted if its parent company, MGL, provided a guarantee to the defendant, to guarantee the repayment of sums.
The judge, Mr Justice Ramsey, considered in the circumstances it was appropriate to grant a stay of execution but that a bond or guarantee provided by a party could be sufficient security for repayment of judgment sums and represent an alternative to a situation where it would normally be appropriate to grant a stay.
The parties engaged in an examination of the financial viability of MGL to provide the guarantee with the judge finding that it is desirable to be provided with all available necessary information regarding the parent’s financial standing but that there was no general obligation to provide confidential financial information to another party to allow it to decide on solvency and whether to apply for a stay.
Mr Justice Ramsey was satisfied as to the financial position of MGL to provide the guarantee in order to lift the stay of execution temporarily granted. The provision of the guarantee would enable summary judgment to be granted to the claimant of the adjudicator’s award.
Whilst this case is yet another demonstration of the court’s support for the adjudication process and potentially overcoming a stay of execution situation, it should not necessarily be seen as a panacea that the provision of a guarantee will always come to the rescue. For a start, parent company guarantees are of course only available to entities with a parent company and one that is financially sound, as otherwise the guarantee will be worthless.
This article was created by construction lawyer --Najma Dunnett as part of an ongoing series of legal articles. Follow Najma on Twitter to keep up to date with the latest changes in construction law @NDunnett_Cons.
[edit] Related articles on Designing Buildings
- Adjudication.
- Contract.
- Contractor.
- Defects.
- Design and build.
- Pay less notice.
- Set off.
- Sub-contractor.
- Westshield v Buckingham.
[edit] External references
Featured articles and news
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.























Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.