Nomination in construction contracts
In the construction industry, the term nomination typically refers to the selection of a supplier or subcontractor by the client to carry out an element of the works. Nominated sub-contractors or suppliers are imposed on the main contractor after the main contractor has been appointed.
Nomination allows the client to have direct, separate negotiations with suppliers or sub-contractors and to feed their appointment and design input into the main contract after works by the main contractor have commenced.
The mechanism for nomination is an instruction in relation to a prime cost sum to which the main contractor is entitled to add mark up and attendance costs.
The contractual arrangements allowing nomination are very complicated, attempting to cover all possible eventualities both between the client and the main contractor and also between the main contractor and the nominated party.
For more information about specific nomination procedures see:
Nomination is still common on international projects, but some forms of contract in the UK no longer include provision for nomination because of the complexities involved. The use of named sub-contractors and named suppliers is generally considered to be a simpler alternative.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.