Negative lag
Lag is: ‘…the minimum necessary lapse of time between the finish of one activity and the finish of another overlapping activity.' Ref The Society of Construction Law Delay and Disruption Protocol, 2nd edition, published in February 2017 by the Society of Construction Law (UK).
The CIOB Planning Protocol 2021 (CIOB PP21), a technical information sheet published by the Chartered Institute of Building (CIOB) in February 2021, defines negative lag as: ‘An overlap between activities / milestones by way of logic with a duration of less than zero resulting in a degree of parallel working.’
[edit] Related articles on Designing Buildings Wiki
- Accepted programme.
- Activity schedule.
- As-built programme.
- Contractor's master programme.
- Contractor's working schedule.
- Critical path.
- Design programme.
- Lag.
- Negative float.
- Programme for building design and construction (project programme).
- Programme.
- Schedule.
- Short period programme.
- Tender works programme.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
When buildings reflected the local resources available.
CIOB reports 57% are using artificial intelligence technologies.
More of England’s ‘hidden heroes’ will be celebrated.
CIAT calls for retrofit to be a priority.
Version 6 is now available, along with guidance for ECA members.
Post-War Homes: mid-century British architecture. Book review.
CIAT reflects on the party conferences.
CIOB announce the winners of the Art of Building photography competition.
National Scheme of Delegation introduced.
The cost of employing people remains a concern.
Code of Practice for Electrical Energy Storage Systems.
ECA calls on members to comment on draft 4th edition.
Bringing together expertise and creating cultural benefits.
















