High-density floating track slab
Can you pump heavyweight concrete through 500 m of 125 mm pipeline? Andrew Turner discusses the challenges of pumping heavyweight concrete for use in high-density floating track slab (FTS) at Crossrail.
In 2011, we were asked if Camfaud could pump heavyweight concrete through 500 m of 125 mm pipeline? Being honest, we said we didn't know and being foolhardy we added that we would give it a go.
That question was asked at the design stage of the Crossrail project when Arup was trying to solve the potential problem of noise and vibration being transferred from the track slab to the Barbican performing arts centre.
We gave it a go and to everyone’s delight and relief the concrete that went into the hopper of our Schwing concrete pump duly came out of the end of the pipeline into the test shutter.
Fast forward to 2015, and we were asked a very similar question. Can you pump heavyweight concrete through 900 m of 125 mm pipeline? This time we were a bit more confident in our reply: we think so and we’ll be more than happy to try.
The question this time came from the successful bidder for the Crossrail C610 contract, Alstom Transport, TSO and Costain, more commonly known as ATC JV.
Concrete pumping trials:
Before the FTS construction began we worked closely with Crossrail, ATC JV, London Concrete, who had won the contract to supply the concrete, and LKAB Minerals, supplier of the heavyweight aggregate.
After extensive laboratory and batching plant trials the material was put to the test in a series of three pumping trials. These were conducted through increasing pump line lengths: 130 m, 500 m and finally 900 m.
Each of the trial pours was a success with the equipment being equal to the task and the material holding together under pressure without segregating or settling out in the pipeline during delays in the pumping.
Also tested during the pumping trials was Camfaud’s water washout system. On the 900 m pumping trial the pipeline contained 11 m3 of heavyweight concrete weighing 40 tonnes. We aimed to use as much of this concrete in the pour to minimise waste, reducing environmental impact and also the overall cost of the contract. The water washout worked as planned and so was adopted into the pumping scheme.
The success of the trials brought us a contract for the project and so we set about augmenting our static pump fleet and putting together a crew of experienced operators and linesmen.
Concrete pumping at Crossrail:
We pumped the concrete into the track slab from three locations: Bond Street station, Fisher Street access shaft and Farringdon station.
Each of the pump set-ups was different due to the size and configuration of the pumping station. At each site we worked with the temporary works engineers to design the pumping station configuration and particularly to install and secure the high pressure concrete delivery line.
Each pumping station included the water washout system with a dedicated washout pump to push the line clear of material, most of it being used to finish the pour with only a small amount pumped to waste. The water was then blown back to recycling tanks on the surface, treated and used for the next cleaning cycle.
After the trials and the early pours our confidence grew that we would complete the contract even with a few pours at or around our previous record distance of 900 m.
Due to programme changes the operation at Bond Street was extended. This led to the question: can you pump heavyweight concrete through 1,000 m of 125 mm pipeline? Without hesitation, we replied: of course we can.
This article was originally published here by ICE on 13 Sept 2017. It was written by Andrew Turner, Area Manager, Camfaud Concrete Pumps.
--The Institution of Civil Engineers
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
AI and the challenges to intellectual property
The legal landscape of adopting AI now and in the future.
Worrying landscape for Welsh construction SMEs revealed.
In recent risk factor analysis report completed by CIOB.
Construction Sport survey highlights risks of dehydration
Supporting construction workers to avoid dangers.
Can your business afford to ignore mental well-being?
£70 - 100 billion annually in UK construction sector.
Mental health in the construction industry
World Mental Health Day 10 October.
Construction awards provide relief in wake of ISG collapse
Spike in major infrastructure awards, housing up but short of targets, are ISG collapse impacts yet to come.
Biodiversity net gain with related updates and terms
Only 0.5% of applications subject to BNG in the context significant proposed changes to planning.
As political power has shifted from blue to red
Has planning now moved from brown to green?
The role of construction in tackling the biodiversity crisis
New CIOB Nature of Building digital series available now.
The Nature Towns and Cities initiative
Grants of up to 1 million for local councils and partners.
The continued ISG fall out October updates
Where to look for answers to frequently asked questions.
Building safety remediation programme for Wales
With 2024 October progress updates.
In major support package for small businesses.
Conservation and transformation
Reading Ruskin’s cultural heritage. Book review.
Renovating Union Chain Bridge.
AI tools for planning, design, construction and management
A long, continually expanding list, any more to add?