Design management plan
A design management plan can be used to co-ordinate design activities. It should at least cover:
- Design responsibility matrix.
- Schedules of drawings to be produced by each discipline/specialist.
- Design programme, including key dates for reviews and information exchanges.
- Schedules of information required/release dates.
- The size and format of drawing types.
- Procedures for CAD / BIM (see BIM execution plan).
- Estimates of staff hours to be spent by designers on each element or drawing.
- Monitoring of design resources expended compared to planned estimates.
- Initiating procedures for design changes.
- Requirements for collateral warranties.
- Incorporation within the design schedule of key dates for review of design performance to check:
- Compliance with brief.
- Cost acceptance.
- Value engineering analysis.
- Health and safety issues.
- Completeness for tender.
The project manager, may use the agreed design management plan as a basis for monitoring and controlling the design process. However, integration of the work of consultant and specialists lies with the lead designer. For certain elements of the project, different leads may be nominated, however, these roles will always come under the direction of the lead designer for co-ordination.
The text in this article is based on an extract from PROJECT MANAGEMENT, by Eric Stokes and Saleem Akram. The original manual was published in 2008. It was developed within the scope of the LdV program, project number: 2009-1-PL1-LEO05-05016 entitled “Common Learning Outcomes for European Managers in Construction”. It is reproduced here in a slightly modified form with the kind permission of the Chartered Institute of Building.
--CIOB
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Comments
This is a really useful resource for teaching how to discharge the duties of the Principal Designer under CDM 2015.
Like the Principal Contractor, the Principal Designer must "plan, manage and monitor" part of the project delivery, namely the pre-construction phase.
The Principal Contractor (and even the Contractor for smaller less complex projects) must produce a Construction Phase Plan. This makes sense. In order "to plan" you need "a plan".
Since the Principal Designer has a similar duty, there is an implied requirement on the Principal Designer to produce a Design Management Plan, Design Execution Plan or Pre-Construction Phase Plan.
The list of headings provided here is helpful because it shows how to integrate H&S into projects rather than having it as a separate item.
Like many other aspects such as the commercial aspects, professionals need to be continuously mindful of the issues and occasional focussed on them.
Liz Bennett
[email protected]