Design management plan
A design management plan can be used to co-ordinate design activities. It should at least cover:
- Design responsibility matrix.
- Schedules of drawings to be produced by each discipline/specialist.
- Design programme, including key dates for reviews and information exchanges.
- Schedules of information required/release dates.
- The size and format of drawing types.
- Procedures for CAD / BIM (see BIM execution plan).
- Estimates of staff hours to be spent by designers on each element or drawing.
- Monitoring of design resources expended compared to planned estimates.
- Initiating procedures for design changes.
- Requirements for collateral warranties.
- Incorporation within the design schedule of key dates for review of design performance to check:
- Compliance with brief.
- Cost acceptance.
- Value engineering analysis.
- Health and safety issues.
- Completeness for tender.
The project manager, may use the agreed design management plan as a basis for monitoring and controlling the design process. However, integration of the work of consultant and specialists lies with the lead designer. For certain elements of the project, different leads may be nominated, however, these roles will always come under the direction of the lead designer for co-ordination.
The text in this article is based on an extract from PROJECT MANAGEMENT, by Eric Stokes and Saleem Akram. The original manual was published in 2008. It was developed within the scope of the LdV program, project number: 2009-1-PL1-LEO05-05016 entitled “Common Learning Outcomes for European Managers in Construction”. It is reproduced here in a slightly modified form with the kind permission of the Chartered Institute of Building.
--CIOB
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
Comments
This is a really useful resource for teaching how to discharge the duties of the Principal Designer under CDM 2015.
Like the Principal Contractor, the Principal Designer must "plan, manage and monitor" part of the project delivery, namely the pre-construction phase.
The Principal Contractor (and even the Contractor for smaller less complex projects) must produce a Construction Phase Plan. This makes sense. In order "to plan" you need "a plan".
Since the Principal Designer has a similar duty, there is an implied requirement on the Principal Designer to produce a Design Management Plan, Design Execution Plan or Pre-Construction Phase Plan.
The list of headings provided here is helpful because it shows how to integrate H&S into projects rather than having it as a separate item.
Like many other aspects such as the commercial aspects, professionals need to be continuously mindful of the issues and occasional focussed on them.
Liz Bennett
[email protected]