Common mistakes in bill of quantities
A bill of quantities (sometimes referred to as 'BoQ' or 'BQ') is a document prepared by a cost consultant (often a quantity surveyor) that provides project-specific measured quantities of the items identified by the drawings and specifications in the tender documentation for construction works.
It is very important that bills of quantities are prepared according to a standard, widely recognised methodology. This helps avoid any ambiguities or misunderstandings and so helps avoid disputes arising through different interpretations of what has been priced.
However, there are some common mistakes that can be made in the bill of quantities. These include:
- Inaccurate measurement of quantities.
- The inclusion of irrelevant preliminary items (this can be due to using preliminary items from a previous project which, although it may be similar, contains differences in scope).
- Insufficient information given in the descriptions.
- Omissions and discrepancies between the BoQ and the drawings or specifications (perhaps due to out-of-date or inaccurate information being used).
- Omissions or double-counting of items (this can be due to more than one quantity surveyor working on the same bill).
- Omission of temporary works items.
There can also be errors made in the pricing, such as:
- Incorrect understanding of the work method.
- Past performance used to assume future productivity.
- Inexperience of the estimator.
- Ignoring the relationship between items of work.
- Changes that are made late in the process.
- Inaccurate assumptions regarding items in the BoQ.
- Arithmetic errors.
- Differences in currencies not considered.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Advantages of a bill of quantities.
- Approximate bill of quantities.
- Bill of quantities.
- Bill of quantities software.
- Common mistakes in construction tenders.
- Cost plans.
- Cost overruns.
- Elemental bill of quantities.
- Estimate.
- How to take off construction works.
- Measurement.
- Taking off.
- Types of bill of quantities.
Featured articles and news
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.