Alternative site assessment ASA
Contents |
[edit] Introduction
An Environmental Impact Assessment (EIA) ensures that the environmental effects of a proposed development are properly considered. For more information see: Environmental Impact Assessment. It provides the local planning authority with better information about certain types of projects, enabling them to make a more informed decision about whether permission should be granted and to allow imposition of more appropriate conditions and obligations to mitigate possible negative impacts.
It will typically include assessment of appropriate alternatives, including an alternative site assessment (ASA).
[edit] Purpose
The purpose of an ASA is to explore whether or not the site proposed for a development is the most suitable one, or whether alternative sites could be preferable.
Due to the impact they may have on the outcome of the planning process, it is important to have ASAs undertaken during the very early stages of a project - not as a process of post-rationalisation after a site has already been selected, and very early appraisals of potential sites may be carried out by a surveyor before the appointment of the consultant team during the business justification stage.
[edit] ASA guidance
There is no formally prescribed process or methodology for undertaking an ASA. The process should be adapted to the characteristics of different projects. However, the Surrey County Council offers suggested stages of an ASA, including:
[edit] Assessment of requirements
- Physical, including size of site and building requirements.
- Access, including distance to and from roads.
- Location, including desirability based on the existing or proposed area of operations.
- Relationships, including proximity to any existing/remaining premises, suppliers, markets.
[edit] Criteria for ASAs
- Whether the site is previously developed land or in active use for the proposed development.
- Likely visual impact.
- Standard of access.
- Likely impact on residential amenities.
- Distance from designated (i.e. environmentally sensitive) areas.
- Flood risk.
- Site availability (e.g. evidence of whether the site is listed for sale).
[edit] Related articles on Designing Buildings
Featured articles and news
Not buildings. Happy holiday from DB.
Future Homes Standard: Industry calls for more ambition
As the Government FHS consultation finally closes.
Improving government projects with data and AI
Enabling better outcomes, efficient modern delivery and influential leadership on government projects.
BSRIA Living Laboratory Innovation Challenge
Final days for submission, closing March 29.
Windows, their frames, forms, factors and functions.
The hidden subtleties of U-Value calculations
Different contexts and what to include as variables.
A brief run down with related articles.
Electrical sector calls for safer public EV charge points
Serious concerns about electrical safety in the public domain.
Building Blocks manifesto presented to parliament
Architects Declare call in for support of five critical policies.
The four elements of project management with APM
Analysis, expectations, collaborative communication and partnerships.
City of London launches Heritage Building Retrofit Toolkit
Empowering owners to initiate necessary adaptations.
Guidance on RAAC in listed buildings
Published by Purcell, endorsed by IHBC, SPAB and C20.
Learning from the past.
Reluctance to hire people with criminal convictions revealed
Employing People with Criminal Convictions Report.
Tackling unconscious bias; Women's History Month
Personal reflections, as the last week of March approaches.